Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 1 18.00 6.00 6.00 20 Sep 2025 31 Oct 2025 5.96 6.00 100.67 %
SH 1 18.88 10.00 10.00 15 Sep 2025 31 Oct 2025 9.97 10.00 100.30 %
2 36.88 16.00 16.00 15.93 16.00 100.44 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Champawat MDR 5683 पुनावे-सिप्टी-न्याड़ी मोटर मार्ग [ Ch. 0.000 - 18.000] 18.000 6.000 6.00 20 Sep 31 Oct 5.960 6.00 101 17 Oct 10:54 am Pankaj Rai, Assistant Engineer Civil, PD Champawat 3
2 PD Champawat SH 5682 ककरालीगेट ठुलीगाढ़ भैरवमन्दिर राज्य मार्ग [ Ch. 0.000 - 18.875] 18.875 10.000 10.00 15 Sep 31 Oct 9.970 10.00 100 17 Oct 10:04 am Laxman Singh, Assistant Engineer Civil, PD Champawat