All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 75.18 39.00 72.00 20 Sep 2025 31 Oct 2025 38.73 39.00 100.70 %
MDR 1 10.00 3.00 6.00 20 Sep 2025 31 Oct 2025 2.98 3.00 100.67 %
4 85.18 42.00 78.00 41.71 42.00 100.70 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Berinaag SH 5450 डगोली सैलानी दाडिमखेत हडबाड पन्द्रहपाली बालीघाट दोफाड धरमघर कोटमन्या पाखू थल सातसिलिग राज्य मार्ग [ Ch. 106.040 - 132.540] 26.500 12.000 24.00 20 Sep 31 Oct 11.920 12.00 101 05 Oct 11:41 am Shravan Kumar Dixit, Assistant Engineer Civil, TD Berinaag 5
2 TD Berinaag SH 7872 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 105.000 - 125.000] 20.000 15.000 24.00 20 Sep 31 Oct 14.890 15.00 101 13 Oct 13:23 pm Shravan Kumar Dixit, Assistant Engineer Civil, TD Berinaag 3
3 TD Berinaag SH 5425 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 61.325 - 90.000] 28.675 12.000 24.00 20 Sep 31 Oct 11.920 12.00 101 17 Oct 10:28 am Deepak Singh Koranga, Assistant Engineer Civil, Engineer-in-Chief Office 4
4 TD Berinaag MDR 5758 दशाईथल खिरमाण्डे नैनी सेराघाट मोटर मार्ग [ Ch. 33.000 - 43.000] 10.000 3.000 6.00 20 Sep 31 Oct 2.980 3.00 101 14 Oct 12:04 pm Deepak Singh Koranga, Assistant Engineer Civil, Engineer-in-Chief Office 3