Loading Dashboard...

Back

PD Rudrapur

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
MDR 2 22.69 22.69 53.00 20 Sep 2025 31 Oct 2025 22.69 22.69 100
ODR 6 47.95 47.95 122.00 20 Sep 2025 31 Oct 2025 47.95 47.95 100
Total 8 70.63 70.64 175.00 70.64 70.64 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Rudrapur MDR 5704
किच्छा दरउ मोटर मार्ग
Ch. 1.200 - 10.085
8.885 8.890 23.00 20 Sep 31 Oct 8.890 8.89 100 12 Oct 07:47 Vinod Chandra, Assistant Engineer Civil, PD Rudrapur 17
2 PD Rudrapur MDR 1242
जाफरपुर गुलरभोज मोटर मार्ग
Ch. 0.000 - 13.800
13.800 13.800 30.00 20 Sep 31 Oct 13.800 13.80 100 11 Oct 16:08 Vinod Chandra, Assistant Engineer Civil, PD Rudrapur
3 PD Rudrapur ODR 1260
शिमला पिस्तौर कुरैया मार्ग
Ch. 0.000 - 8.960
8.960 8.960 23.00 20 Sep 31 Oct 8.960 8.96 100 16 Oct 13:07 Manoj Kumar, Assistant Engineer Civil, ADB Div Rudrapur 9
4 PD Rudrapur ODR 1243
गिद्धपुरी वीरूनगला मार्ग ।
Ch. 0.000 - 3.600
3.600 3.600 10.00 20 Sep 31 Oct 3.600 3.60 100 11 Oct 16:09 Vinod Chandra, Assistant Engineer Civil, PD Rudrapur 7
5 PD Rudrapur ODR 1258
भूरारानी छत्तरपुर मटकोटा मार्ग
Ch. 0.000 - 7.000
7.000 7.000 21.00 20 Sep 31 Oct 7.000 7.00 100 11 Oct 16:09 Vinod Chandra, Assistant Engineer Civil, PD Rudrapur
6 PD Rudrapur ODR 1294
मसीत बहार बजीर सैदलीगंज मिसिंग लिंक
Ch. 0.000 - 10.700
10.700 10.700 25.00 20 Sep 31 Oct 10.700 10.70 100 16 Oct 21:51 Vinod Chandra, Assistant Engineer Civil, PD Rudrapur
7 PD Rudrapur ODR 1278
गदरपुर बलरामनगर सैदलीगंज मार्ग
Ch. 0.000 - 9.685
9.685 9.690 22.00 20 Sep 31 Oct 9.690 9.69 100 16 Oct 21:53 Vinod Chandra, Assistant Engineer Civil, PD Rudrapur
8 PD Rudrapur ODR 1277
गदरपुर मिलकखानम मार्ग
Ch. 0.000 - 8.000
8.000 8.000 21.00 20 Sep 31 Oct 8.000 8.00 100 16 Oct 13:06 Manoj Kumar, Assistant Engineer Civil, ADB Div Rudrapur