All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 49.00 16.00 25.00 20 Sep 2025 31 Oct 2025 15.88 16.00 100.76 %
MDR 1 16.00 12.00 15.00 20 Sep 2025 31 Oct 2025 11.92 12.00 100.67 %
3 65.00 28.00 40.00 27.80 28.00 100.72 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Uttarkashi SH 5461 देवीधार धनारी फ़ोल्ड संकुणाधार राज्य मार्ग [ Ch. 0.000 - 24.000] 24.000 11.000 15.00 20 Sep 31 Oct 10.920 11.00 101 04 Oct 12:45 pm Pankaj Kumar, Assistant Engineer Civil, PD Uttarkashi
2 PD Uttarkashi SH 5546 सिलक्यारा बनगांव चापड़ा सरोठ राज्य मार्ग [ Ch. 0.000 - 25.000] 25.000 5.000 10.00 20 Sep 31 Oct 4.960 5.00 101 14 Oct 10:35 am Laxmi Kant Gupta, Assistant Engineer Civil, PD Uttarkashi 9
3 PD Uttarkashi MDR 5706 ब्रहमखाल जुणगा कुमारकोट मोटर मार्ग [ Ch. 0.000 - 16.000] 16.000 12.000 15.00 20 Sep 31 Oct 11.920 12.00 101 14 Oct 10:36 am Laxmi Kant Gupta, Assistant Engineer Civil, PD Uttarkashi 6