Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 18.00 10.00 15.00 20 Sep 2025 31 Oct 2025 9.93 10.00 100.70 %
MDR 1 12.76 5.00 5.00 20 Sep 2025 31 Oct 2025 4.96 5.00 100.81 %
ODR 1 10.00 5.00 6.00 20 Sep 2025 31 Oct 2025 4.96 5.00 100.81 %
3 40.76 20.00 26.00 19.85 20.00 100.76 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Bhatwari SH 5562 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 0.000 - 18.000] 18.000 10.000 15.00 20 Sep 31 Oct 9.930 10.00 101 16 Oct 22:23 pm Swaraj Chauhan, Assistant Engineer Civil, PD Bhatwari 5
2 PD Bhatwari MDR 5652 तेखला महिडाण्डा मोटर मार्ग [ Ch. 0.000 - 12.760] 12.760 5.000 5.00 20 Sep 31 Oct 4.960 5.00 101 16 Oct 22:24 pm Swaraj Chauhan, Assistant Engineer Civil, PD Bhatwari 5
3 PD Bhatwari ODR 1915 भटवाड़ी बार्सू मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 5.000 6.00 20 Sep 31 Oct 4.960 5.00 101 21 Oct 16:16 pm Anil Kumar, Assistant Engineer Civil, PD Bhatwari