Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 2 107.50 33.00 62.00 20 Sep 2025 31 Oct 2025 33.00 33.00 100
MDR 1 32.17 21.00 35.00 20 Sep 2025 31 Oct 2025 21.00 21.00 100
ODR 1 15.00 5.00 10.00 20 Sep 2025 31 Oct 2025 5.00 5.00 100
Total 4 154.67 59.00 107.00 59.00 59.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Uttarkashi SH 5436
बड़ेथी बनचौरा बद्रीगाड राज्य मार्ग
Ch. 0.000 - 53.400
53.400 20.000 32.00 20 Sep 31 Oct 20.000 20.00 100 16 Oct 10:42 Taqdir Singh, Assistant Engineer Civil, CD Uttarkashi 4
2 CD Uttarkashi SH 5547
सिलक्यारा बनगांव चापड़ा सरोठ राज्य मार्ग
Ch. 25.000 - 79.100
54.100 13.000 30.00 20 Sep 31 Oct 13.000 13.00 100 05 Oct 11:14 Taqdir Singh, Assistant Engineer Civil, CD Uttarkashi 5
3 CD Uttarkashi MDR 5656
धरासू देवीसौड़ मल्ली बैण्ड.से जोगथ मोटर मार्ग।
Ch. 7.432 - 39.600
32.168 21.000 35.00 20 Sep 31 Oct 21.000 21.00 100 15 Oct 10:34 Monika Chauhan, Assistant Engineer Civil, CD Uttarkashi 3
4 CD Uttarkashi ODR 1946
बनचौरा बनगांव मोटर मार्ग
Ch. 0.000 - 15.000
15.000 5.000 10.00 20 Sep 31 Oct 5.000 5.00 100 21 Oct 13:39 Taqdir Singh, Assistant Engineer Civil, CD Uttarkashi