All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 107.50 33.00 62.00 20 Sep 2025 31 Oct 2025 32.77 33.00 100.70 %
MDR 1 32.17 21.00 35.00 20 Sep 2025 31 Oct 2025 20.85 21.00 100.72 %
ODR 1 15.00 5.00 10.00 20 Sep 2025 31 Oct 2025 4.96 5.00 100.81 %
4 154.67 59.00 107.00 58.58 59.00 100.72 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Uttarkashi SH 5436 बड़ेथी बनचौरा बद्रीगाड राज्य मार्ग [ Ch. 0.000 - 53.400] 53.400 20.000 32.00 20 Sep 31 Oct 19.860 20.00 101 16 Oct 10:24 am Taqdir Singh, Assistant Engineer Civil, CD Uttarkashi 4
2 CD Uttarkashi SH 5547 सिलक्यारा बनगांव चापड़ा सरोठ राज्य मार्ग [ Ch. 25.000 - 79.100] 54.100 13.000 30.00 20 Sep 31 Oct 12.910 13.00 101 05 Oct 10:56 am Taqdir Singh, Assistant Engineer Civil, CD Uttarkashi 5
3 CD Uttarkashi MDR 5656 धरासू देवीसौड़ मल्ली बैण्ड.से जोगथ मोटर मार्ग। [ Ch. 7.432 - 39.600] 32.168 21.000 35.00 20 Sep 31 Oct 20.850 21.00 101 15 Oct 10:16 am Monika Chauhan, Assistant Engineer Civil, CD Uttarkashi 3
4 CD Uttarkashi ODR 1946 बनचौरा बनगांव मोटर मार्ग [ Ch. 0.000 - 15.000] 15.000 5.000 10.00 20 Sep 31 Oct 4.960 5.00 101 21 Oct 13:21 pm Taqdir Singh, Assistant Engineer Civil, CD Uttarkashi