All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 106.15 69.00 103.00 20 Sep 2025 30 Oct 2025 68.59 69.00 100.60 %
2 106.15 69.00 103.00 68.59 69.00 100.60 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Purola SH 5559 त्यूनी पुरोला नौगांव राज्य मार्ग [ Ch. 20.000 - 84.000] 64.000 27.000 75.00 20 Sep 30 Oct 26.840 27.00 101 21 Oct 18:57 pm Govind Singh Rawat, Assistant Engineer Civil, CD Purola 6