Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
MDR 2 75.00 30.00 45.00 20 Sep 2025 31 Oct 2025 30.00 30.00 100
Total 2 75.00 30.00 45.00 30.00 30.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Badkote MDR 5607
नौगांव पौन्टी राजगढ़ी गंगताड़ी सरनौल मोटर मार्ग
Ch. 0.000 - 51.000
51.000 24.000 36.00 20 Sep 31 Oct 24.000 24.00 100 21 Oct 10:35 Sitaram Dobhal, Assistant Engineer Civil, CD Barkot 7
2 CD Badkote MDR 5610
डामटा कण्डारी सारीगाड़ मोटर मार्ग
Ch. 0.000 - 24.000
24.000 6.000 9.00 20 Sep 31 Oct 6.000 6.00 100 21 Oct 13:07 Mahesh Kumar, Assistant Engineer Civil, CD Barkot