Loading Dashboard...
Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | CD Badkote | MDR | 5607 |
नौगांव पौन्टी राजगढ़ी गंगताड़ी सरनौल मोटर मार्ग
Ch. 0.000 - 51.000
|
51.000 | 24.000 | 36.00 | 20 Sep | 31 Oct | 24.000 | 24.00 | 100 | 21 Oct 10:35 | Sitaram Dobhal, Assistant Engineer Civil, CD Barkot | 7 |
| 2 | CD Badkote | MDR | 5610 |
डामटा कण्डारी सारीगाड़ मोटर मार्ग
Ch. 0.000 - 24.000
|
24.000 | 6.000 | 9.00 | 20 Sep | 31 Oct | 6.000 | 6.00 | 100 | 21 Oct 13:07 | Mahesh Kumar, Assistant Engineer Civil, CD Barkot |