Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | PD Karnprayag | MDR | 2128 |
नन्दप्रयाग-घाट घाट सुतोल कनोल मोटर मार्ग
Ch. 0.000 - 48.690
|
48.690 | 11.000 | 15.94 | 20 Sep | 31 Oct | 11.000 | 11.00 | 100 | 16 Oct 09:46 | Gyanendra Kumar, Assistant Engineer Civil, PD Karnprayag | 12 |
| 2 | PD Karnprayag | ODR | 2132 |
सेमा बैराऊ मोटर मार्ग (थिरपाक काण्डई बैरासकुण्ड मोटर मार्ग)
Ch. 0.000 - 10.570
|
10.570 | 6.000 | 4.50 | 20 Sep | 31 Oct | 6.000 | 6.00 | 100 | 23 Oct 12:53 | Yogesh Chandra Pant, Assistant Engineer Civil, PD Karnprayag |