Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | CD Tharali | SH | 5623 |
नंदा देवी राजजात मार्ग (थराली देवाल मुन्दोली वाण राज्य मार्ग)
Ch. 0.000 - 52.200
|
52.200 | 5.000 | 12.50 | 20 Sep | 31 Oct | 5.000 | 7.50 | 150 | 23 Oct 13:57 | Jagdesh Kumar Tamta, Assistant Engineer Civil, CD Tharali | 4 |
| 2 | CD Tharali | SH | 5624 |
ग्वालदम नन्दकेशरी राज्य मार्ग
Ch. 0.000 - 18.000
|
18.000 | 5.000 | 12.50 | 20 Sep | 31 Oct | 5.000 | 5.00 | 100 | 24 Oct 08:18 | Jagdesh Kumar Tamta, Assistant Engineer Civil, CD Tharali |