Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | TD Gaucher | SH | 5476 |
कर्णप्रयाग नौटी पैठाणी राज्य मार्ग
Ch. 0.000 - 47.150
|
47.150 | 23.000 | 18.40 | 20 Sep | 31 Oct | 23.000 | 41.00 | 178 | 17 Oct 20:57 | Mohammad Rashid, Assistant Engineer Civil, CD Gaucher | 3 |
| 2 | TD Gaucher | SH | 2186 |
कर्णप्रयाग धारदुंगी मैखूरा कंडारा सोनला राज्य मार्ग
Ch. 0.000 - 44.850
|
44.850 | 30.000 | 22.00 | 20 Sep | 31 Oct | 30.000 | 25.00 | 83 | 16 Oct 09:52 | Mohammad Rashid, Assistant Engineer Civil, CD Gaucher | 1 |
| 3 | TD Gaucher | SH | 5626 |
गौचर सिदोली राज्य मार्ग
Ch. 0.000 - 24.500
|
24.500 | 10.000 | 7.50 | 20 Sep | 31 Oct | 10.000 | 10.00 | 100 | 23 Oct 12:56 | Vishal Raj, Assistant Engineer Civil, Engineer-in-Chief Office | 18 |
| 4 | TD Gaucher | SH | 5622 |
आदिबद्री नौटी राज्य मार्ग
Ch. 0.000 - 38.530
|
38.530 | 32.000 | 22.10 | 20 Sep | 31 Oct | 32.000 | 32.00 | 100 | 22 Oct 20:09 | Vishal Raj, Assistant Engineer Civil, Engineer-in-Chief Office |