All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 4 105.59 41.00 62.00 20 Sep 2025 31 Oct 2025 40.71 42.00 103.17 %
MDR 1 19.80 19.80 22.00 20 Sep 2025 31 Oct 2025 19.66 19.80 100.71 %
5 125.39 60.80 84.00 60.37 61.80 102.37 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Rudraprayag SH 5487 पौड़ी खिर्सू खेडाखाल खांखरा राज्य मार्ग [ Ch. 32.220 - 54.820] 22.600 7.000 14.00 20 Sep 31 Oct 6.950 9.00 129 23 Oct 14:58 pm Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag
2 PD Rudraprayag SH 5507 मयाली-गुप्तकाशी राज्य मार्ग(जखोली-भीरी- गुप्तकाशी व मयाली-जखोली मार्ग) [ Ch. 0.000 - 39.000] 39.000 11.000 20.00 20 Sep 31 Oct 10.920 12.00 110 16 Oct 09:17 am Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag 23
3 PD Rudraprayag SH 5560 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 129.250 - 167.040] 37.790 23.000 28.00 20 Sep 31 Oct 22.840 21.00 92 18 Oct 09:40 am Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag 23
4 PD Rudraprayag MDR 2244 विजयनगर तैला मोटर मार्ग [ Ch. 0.000 - 19.800] 19.800 19.800 22.00 20 Sep 31 Oct 19.660 19.80 101 18 Oct 09:40 am Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag 11
5 PD Rudraprayag SH 8705 मयाली-गुप्तकाशी राज्य मार्ग(जखोली-भीरी- गुप्तकाशी व मयाली-जखोली मार्ग) [ Ch. 65.150 - 71.350] 6.200 0.000 0.00 20 Sep 31 Oct 0.000 - - 6