PD Rudraprayag

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 4 105.59 41.00 62.00 20 Sep 2025 31 Oct 2025 41.00 44.00 107.32
MDR 1 19.80 19.80 22.00 20 Sep 2025 31 Oct 2025 19.80 19.80 100
Total 5 125.39 60.80 84.00 60.80 63.80 104.93

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Rudraprayag SH 5487
पौड़ी खिर्सू खेडाखाल खांखरा राज्य मार्ग
Ch. 32.220 - 54.820
22.600 7.000 14.00 20 Sep 31 Oct 7.000 9.00 129 23 Oct 15:16 Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag
2 PD Rudraprayag SH 5507
मयाली-गुप्तकाशी राज्य मार्ग(जखोली-भीरी- गुप्तकाशी व मयाली-जखोली मार्ग)
Ch. 0.000 - 39.000
39.000 11.000 20.00 20 Sep 31 Oct 11.000 12.00 109 16 Oct 09:35 Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag 23
3 PD Rudraprayag SH 5560
उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग
Ch. 129.250 - 167.040
37.790 23.000 28.00 20 Sep 31 Oct 23.000 23.00 100 29 Oct 10:38 Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag 23
4 PD Rudraprayag MDR 2244
विजयनगर तैला मोटर मार्ग
Ch. 0.000 - 19.800
19.800 19.800 22.00 20 Sep 31 Oct 19.800 19.80 100 18 Oct 09:58 Sanjay Kumar Saini, Assistant Engineer Civil, PD Rudraprayag 11
5 PD Rudraprayag SH 8705
मयाली-गुप्तकाशी राज्य मार्ग(जखोली-भीरी- गुप्तकाशी व मयाली-जखोली मार्ग)
Ch. 65.150 - 71.350
6.200 0.000 0.00 20 Sep 31 Oct 0.000 - 0 6