Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | CD Ukhimath | SH | 5508 |
मयाली-गुप्तकाशी राज्य मार्ग(जखोली-भीरी- गुप्तकाशी व मयाली-जखोली मार्ग)
Ch. 39.000 - 65.150
|
26.150 | 6.000 | 13.00 | 20 Sep | 31 Oct | 6.000 | 8.00 | 133 | 12 Oct 17:12 | Lalit Kumar, Assistant Engineer Civil, CD Ukhimath | 11 |
| 2 | CD Ukhimath | SH | 5434 |
बासंवाडा कणसिल चन्द्रनगर मोहनखाल राज्य मार्ग
Ch. 0.000 - 30.010
|
30.010 | 12.000 | 24.00 | 20 Sep | 31 Oct | 12.000 | 12.00 | 100 | 16 Oct 20:35 | Anuj Bhardwaj, Assistant Engineer Civil, CD Ukhimath | 2 |
| 3 | CD Ukhimath | SH | 5645 |
गुप्तकाशी कालीमठ कोटमा जाल मल्ला चौमासी राज्य मार्ग
Ch. 0.000 - 24.850
|
24.850 | 13.000 | 26.00 | 20 Sep | 31 Oct | 13.000 | 13.00 | 100 | 24 Oct 07:49 | Narendra Kumar, Assistant Engineer Civil, CD Ukhimath | 12 |