All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 128.75 50.00 100.00 20 Sep 2025 31 Oct 2025 49.64 50.00 100.73 %
MDR 2 79.05 35.00 70.00 20 Sep 2025 31 Oct 2025 34.75 35.00 100.72 %
ODR 10 85.89 64.00 132.00 20 Sep 2025 31 Oct 2025 63.55 64.04 100.77 %
15 293.68 149.00 302.00 147.94 149.04 100.74 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD New Tehri SH 5553 टिहरी हिण्डोलाखाल देवप्रयाग व्यासघाट बिलखेत राज्य मार्ग [ Ch. 0.000 - 31.000] 31.000 11.000 22.00 20 Sep 31 Oct 10.920 11.00 101 15 Oct 10:24 am Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri 30
2 PD New Tehri SH 5496 लम्बगांव मोटना रजाखेत घनसाली सेन्दुल राज्य मार्ग [ Ch. 0.000 - 81.400] 81.400 25.000 50.00 20 Sep 31 Oct 24.820 25.00 101 23 Oct 13:54 pm Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri 21
3 PD New Tehri SH 5564 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 50.775 - 67.125] 16.350 14.000 28.00 20 Sep 31 Oct 13.900 14.00 101 17 Oct 10:14 am Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri 3
4 PD New Tehri MDR 5673 लम्बगांव प्रतापनगर टिहरी मोटर मार्ग [ Ch. 0.000 - 51.845] 51.845 21.000 42.00 20 Sep 31 Oct 20.850 21.00 101 23 Oct 15:16 pm Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri 6
5 PD New Tehri MDR 7874 राइफलमेन स्व० दीवान सिंह बागड़ी मोटर मार्ग (रौडधार पौडीखाल गड़ाकोट जाखणीधार मोटर मार्ग) [ Ch. 16.730 - 43.930] 27.200 14.000 28.00 20 Sep 31 Oct 13.900 14.00 101 16 Oct 09:48 am Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri 9
6 PD New Tehri ODR 2377 चौधार औखला मोटर मार्ग [ Ch. 0.000 - 9.600] 9.600 9.000 18.00 20 Sep 31 Oct 8.940 9.00 101 16 Oct 10:29 am Vedpal Singh Pawar, Assistant Engineer Civil, Engineer-in-Chief Office
7 PD New Tehri ODR 2380 नई टिहरी के आन्तरिक मार्ग [ Ch. 0.000 - 3.000] 3.000 3.000 6.00 20 Sep 31 Oct 2.980 3.00 101 29 Sep 11:38 am Vandana Kundliya, Assistant Engineer Civil, PD New Tehri 4
8 PD New Tehri ODR 10049 नई टिहरी के आन्तरिक मार्ग [ Ch. 0.000 - 1.600] 1.600 1.600 3.20 20 Sep 31 Oct 1.590 1.60 101 29 Sep 11:39 am Vandana Kundliya, Assistant Engineer Civil, PD New Tehri 2
9 PD New Tehri ODR 10050 नई टिहरी के आन्तरिक मार्ग [ Ch. 0.000 - 1.330] 1.330 1.300 2.60 20 Sep 31 Oct 1.290 1.33 103 29 Sep 14:55 pm Vandana Kundliya, Assistant Engineer Civil, PD New Tehri
10 PD New Tehri ODR 10051 नई टिहरी के आन्तरिक मार्ग [ Ch. 0.000 - 3.107] 3.107 3.100 6.20 20 Sep 31 Oct 3.080 3.11 101 29 Sep 13:45 pm Vandana Kundliya, Assistant Engineer Civil, PD New Tehri 2
11 PD New Tehri ODR 2401 निरालीधार दपोली सुनाली मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 8.000 16.00 20 Sep 31 Oct 7.940 8.00 101 16 Oct 09:47 am Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri
12 PD New Tehri ODR 2403 जीरोब्रिज चौपडा सैण पिपोला मोटर मार्ग [ Ch. 0.000 - 10.250] 10.250 8.000 16.00 20 Sep 31 Oct 7.940 8.00 101 26 Oct 17:49 pm Vandana Kundliya, Assistant Engineer Civil, PD New Tehri
13 PD New Tehri ODR 2453 सैण मंदार घोल्डानी मोटर मार्ग [ Ch. 0.000 - 19.750] 19.750 12.000 24.00 20 Sep 31 Oct 11.920 12.00 101 08 Oct 10:10 am Vedpal Singh Pawar, Assistant Engineer Civil, Engineer-in-Chief Office
14 PD New Tehri ODR 2426 लम्बगांव विजपुर रावतगांव पनियाला मोटर मार्ग [ Ch. 0.000 - 17.250] 17.250 10.000 24.00 20 Sep 31 Oct 9.930 10.00 101 23 Oct 15:17 pm Satish Chandra Bhatt, Assistant Engineer Civil, PD New Tehri 4
15 PD New Tehri ODR 2381 पिपलडाली रजाखेत मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 8.000 16.00 20 Sep 31 Oct 7.940 8.00 101 16 Oct 19:38 pm Vedpal Singh Pawar, Assistant Engineer Civil, Engineer-in-Chief Office