Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 161.50 37.00 83.00 20 Sep 2025 31 Oct 2025 37.00 49.00 132.43
ODR 2 7.06 4.00 10.00 20 Sep 2025 31 Oct 2025 4.00 4.93 123.25
Total 5 168.56 41.00 93.00 41.00 53.93 131.54

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Narendnagar SH 5515
नरेन्द्रनगर रानीपोखरी राज्य मार्ग
Ch. 0.000 - 17.000
17.000 9.000 22.50 20 Sep 31 Oct 9.000 17.00 189 31 Oct 16:40 Satya Prakash, Assistant Engineer Civil, CD Dugadda 10
2 CD Narendnagar SH 5518
पौड़ी देवप्रयाग गजा जाजल राज्य मार्ग
Ch. 49.000 - 119.500
70.500 8.000 18.00 20 Sep 31 Oct 8.000 12.00 150 17 Oct 08:35 Ashwani Kumar Yadav, Assistant Engineer Civil, CD Narendnagar 15
3 CD Narendnagar SH 5465
गूलर नाई सिलखणी मठियाली पसरखेत तमियार गजा तिमली शिवपुरी राज्य मार्ग
Ch. 0.000 - 74.000
74.000 20.000 42.50 20 Sep 31 Oct 20.000 20.00 100 31 Oct 16:08 Ashwani Kumar Yadav, Assistant Engineer Civil, CD Narendnagar 14
4 CD Narendnagar ODR 2483
ऋषिकेश-गंगोत्री मो0 मार्ग
Ch. 13.780 - 18.090
4.310 2.000 5.00 20 Sep 31 Oct 2.000 2.93 147 23 Oct 21:35 Gaurav Juyal, Assistant Engineer Civil, CD Narendnagar 14
5 CD Narendnagar ODR 2488
विठ्ठल आश्रम मोटर मार्ग
Ch. 0.000 - 2.750
2.750 2.000 5.00 20 Sep 31 Oct 2.000 2.00 100 15 Oct 15:35 Ashwani Kumar Yadav, Assistant Engineer Civil, CD Narendnagar 1