TD Ghansali

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 114.13 38.00 60.80 20 Sep 2025 31 Oct 2025 38.00 40.00 105.26
MDR 2 96.08 29.00 46.50 20 Sep 2025 31 Oct 2025 29.00 30.00 103.45
Total 5 210.20 67.00 107.30 67.00 70.00 104.48

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 TD Ghansaali SH 5565
उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग
Ch. 67.125 - 129.250
62.125 20.000 24.80 20 Sep 31 Oct 20.000 20.00 100 15 Oct 15:32 Ankit Bhatt, Assistant Engineer Civil, TD Ghansali 66
2 TD Ghansaali SH 5459
कमद धौन्तरी चमियाला बुढाकेदार अंयारखाल राज्य मार्ग
Ch. 17.800 - 51.800
34.000 9.000 18.00 20 Sep 31 Oct 9.000 9.00 100 28 Oct 09:50 Mahak Singh, Assistant Engineer Civil, TD Ghansali 5
3 TD Ghansaali SH 5468
जाखधार घनसाली राज्य मार्ग
Ch. 0.000 - 18.000
18.000 9.000 18.00 20 Sep 31 Oct 9.000 11.00 122 18 Oct 14:17 Sunit Kumar, Assistant Engineer Civil, Engineer-in-Chief Office 39
4 TD Ghansaali MDR 5658
घनसाली घुत्तू मोटर मार्ग
Ch. 0.000 - 30.300
30.300 15.000 24.50 20 Sep 31 Oct 15.000 16.00 107 23 Oct 12:52 Vikas Kumar, Assistant Engineer Civil, TD Ghansali 10
5 TD Ghansaali MDR 5659
घनसाली कोटी अखोड़ी हुलानाखाल मुलगढ मोटर मार्ग
Ch. 0.000 - 65.775
65.775 14.000 22.00 20 Sep 31 Oct 14.000 14.00 100 16 Oct 19:06 Mahak Singh, Assistant Engineer Civil, TD Ghansali 9