Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 2 83.00 17.00 53.91 20 Sep 2025 31 Oct 2025 17.00 21.00 123.53
MDR 1 45.50 25.00 50.00 20 Sep 2025 31 Oct 2025 25.00 25.00 100
ODR 1 19.00 4.00 8.00 20 Sep 2025 31 Oct 2025 4.00 6.00 150
Total 4 147.50 46.00 111.91 46.00 52.00 113.04

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 TD Kirtinagar SH 5503
लक्ष्मोली हिंसरियाखाल जामणीखाल बागवान मोटर मार्ग
Ch. 0.000 - 57.000
57.000 13.000 48.91 20 Sep 31 Oct 13.000 16.00 123 23 Oct 15:43 Niki Bala, Assistant Engineer Civil, TD Kirtinagar 37
2 TD Kirtinagar SH 5552
टिहरी हिण्डोलाखाल देवप्रयाग व्यासघाट बिलखेत राज्य मार्ग
Ch. 31.000 - 57.000
26.000 4.000 5.00 20 Sep 31 Oct 4.000 5.00 125 23 Oct 15:28 Yatendra Singh Rawat, Assistant Engineer Civil, TD Kirtinagar 12
3 TD Kirtinagar MDR 5680
कीर्तिनगर बडियार धोडंगी सौराखाल मोटर मार्ग
Ch. 0.000 - 45.500
45.500 25.000 50.00 20 Sep 31 Oct 25.000 25.00 100 23 Oct 15:16 Niki Bala, Assistant Engineer Civil, TD Kirtinagar 31
4 TD Kirtinagar ODR 2771
नागचौड़ चामी तोली पीपलीधार मोटर मार्ग
Ch. 0.000 - 19.000
19.000 4.000 8.00 20 Sep 31 Oct 4.000 6.00 150 23 Oct 15:28 Yatendra Singh Rawat, Assistant Engineer Civil, TD Kirtinagar 28