All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 83.00 17.00 53.91 20 Sep 2025 31 Oct 2025 17.00 21.00 123.53 %
MDR 1 45.50 25.00 50.00 20 Sep 2025 31 Oct 2025 25.00 25.00 100.00 %
ODR 1 19.00 4.00 8.00 20 Sep 2025 31 Oct 2025 4.00 6.00 150.00 %
4 147.50 46.00 111.91 46.00 52.00 113.04 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Kirtinagar SH 5503 लक्ष्मोली हिंसरियाखाल जामणीखाल बागवान मोटर मार्ग [ Ch. 0.000 - 57.000] 57.000 13.000 48.91 20 Sep 31 Oct 13.000 16.00 123 23 Oct 15:25 pm Niki Bala, Assistant Engineer Civil, TD Kirtinagar 37
2 TD Kirtinagar SH 5552 टिहरी हिण्डोलाखाल देवप्रयाग व्यासघाट बिलखेत राज्य मार्ग [ Ch. 31.000 - 57.000] 26.000 4.000 5.00 20 Sep 31 Oct 4.000 5.00 125 23 Oct 15:10 pm Yatendra Singh Rawat, Assistant Engineer Civil, TD Kirtinagar 12
3 TD Kirtinagar MDR 5680 कीर्तिनगर बडियार धोडंगी सौराखाल मोटर मार्ग [ Ch. 0.000 - 45.500] 45.500 25.000 50.00 20 Sep 31 Oct 25.000 25.00 100 23 Oct 14:58 pm Niki Bala, Assistant Engineer Civil, TD Kirtinagar 31
4 TD Kirtinagar ODR 2771 नागचौड़ चामी तोली पीपलीधार मोटर मार्ग [ Ch. 0.000 - 19.000] 19.000 4.000 8.00 20 Sep 31 Oct 4.000 6.00 150 23 Oct 15:10 pm Yatendra Singh Rawat, Assistant Engineer Civil, TD Kirtinagar 28