Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 2 105.48 40.00 100.00 20 Sep 2025 31 Oct 2025 40.00 40.00 100
MDR 3 102.93 31.50 78.75 20 Sep 2025 31 Oct 2025 31.50 31.50 100
Total 5 208.41 71.50 178.75 71.50 71.50 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 TD Thathyd SH 5435
बड़ेथी बनचौरा बद्रीगाड राज्य मार्ग
Ch. 53.400 - 94.600
41.200 20.000 50.00 20 Sep 31 Oct 20.000 20.00 100 15 Oct 12:44 Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 92
2 TD Thathyd SH 5526
स्वतंत्रता संग्राम सैनानी श्री विश्वेश्वर दत्त सकलानी मोटर मार्ग (रायपुर कददूखाल राज्य मार्ग)
Ch. 7.500 - 71.780
64.280 20.000 50.00 20 Sep 31 Oct 20.000 20.00 100 16 Oct 17:31 Prashant Bhatt, Assistant Engineer Civil, TD Thatyur 67
3 TD Thathyd MDR 5653
अगलाड थत्यूड अलमस बैन्ड मोटर मार्ग
Ch. 0.000 - 50.500
50.500 11.500 28.75 20 Sep 31 Oct 11.500 11.50 100 27 Oct 13:49 Naveen Kumar Sharma, Assistant Engineer Civil, TD Thatyur 35
4 TD Thathyd MDR 5655
नैनबाग घोडाखुरी ऐन्दी मोटर मार्ग
Ch. 0.000 - 31.000
31.000 7.000 17.50 20 Sep 31 Oct 7.000 7.00 100 29 Sep 13:21 Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 61
5 TD Thathyd MDR 5657
कैम्पटी चडोगी मोटर मार्ग
Ch. 0.000 - 21.431
21.431 13.000 32.50 20 Sep 31 Oct 13.000 13.00 100 23 Oct 12:33 Surendra Kumar, Assistant Engineer Civil, PD New Tehri 17