Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 105.48 40.00 100.00 20 Sep 2025 31 Oct 2025 39.72 40.00 100.70 %
MDR 3 102.93 31.50 78.75 20 Sep 2025 31 Oct 2025 31.28 30.00 95.91 %
5 208.41 71.50 178.75 71.00 70.00 98.59 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Thathyd SH 5435 बड़ेथी बनचौरा बद्रीगाड राज्य मार्ग [ Ch. 53.400 - 94.600] 41.200 20.000 50.00 20 Sep 31 Oct 19.860 20.00 101 15 Oct 12:26 pm Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 79
2 TD Thathyd SH 5526 स्वतंत्रता संग्राम सैनानी श्री विश्वेश्वर दत्त सकलानी मोटर मार्ग (रायपुर कददूखाल राज्य मार्ग) [ Ch. 7.500 - 71.780] 64.280 20.000 50.00 20 Sep 31 Oct 19.860 20.00 101 16 Oct 17:13 pm Prashant Bhatt, Assistant Engineer Civil, TD Thatyur 67
3 TD Thathyd MDR 5653 अगलाड थत्यूड अलमस बैन्ड मोटर मार्ग [ Ch. 0.000 - 50.500] 50.500 11.500 28.75 20 Sep 31 Oct 11.420 10.00 88 23 Oct 15:23 pm Prashant Bhatt, Assistant Engineer Civil, TD Thatyur 21
4 TD Thathyd MDR 5655 नैनबाग घोडाखुरी ऐन्दी मोटर मार्ग [ Ch. 0.000 - 31.000] 31.000 7.000 17.50 20 Sep 31 Oct 6.950 7.00 101 29 Sep 13:03 pm Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 60
5 TD Thathyd MDR 5657 कैम्पटी चडोगी मोटर मार्ग [ Ch. 0.000 - 21.431] 21.431 13.000 32.50 20 Sep 31 Oct 12.910 13.00 101 23 Oct 12:15 pm Surendra Kumar, Assistant Engineer Civil, PD New Tehri 17