Loading Dashboard...

Back

TD Chakrata

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 155.89 55.00 83.00 20 Sep 2025 31 Oct 2025 55.00 55.00 100
MDR 1 48.33 14.00 27.50 20 Sep 2025 31 Oct 2025 14.00 14.00 100
ODR 1 24.75 6.00 27.50 20 Sep 2025 31 Oct 2025 6.00 6.00 100
Total 5 228.97 75.00 138.00 75.00 75.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 TD Chakrata SH 5442
चकराता लाखामण्डल बर्नीगाड राज्य मार्ग
Ch. 0.000 - 65.340
65.340 46.000 55.00 20 Sep 31 Oct 46.000 46.00 100 27 Oct 20:44 Aditya Nath Thakur, Assistant Engineer Civil, TD Chakrata
2 TD Chakrata SH 5558
त्यूनी पुरोला नौगांव राज्य मार्ग
Ch. 0.000 - 20.000
20.000 0.000 0.00 20 Sep 31 Oct 0.000 - 0 3
3 TD Chakrata SH 5452
दारागाड कथियान कांडा राज्य मार्ग
Ch. 0.000 - 70.550
70.550 9.000 28.00 20 Sep 31 Oct 9.000 9.00 100 17 Oct 11:09 Jwala Datt Kandpal, Assistant Engineer Civil, TD Chakrata 5
4 TD Chakrata MDR 5627
पुरोड़ी रावना डामटा मोटर मार्ग
Ch. 0.000 - 48.325
48.325 14.000 27.50 20 Sep 31 Oct 14.000 14.00 100 17 Oct 11:03 Aditya Nath Thakur, Assistant Engineer Civil, TD Chakrata
5 TD Chakrata ODR 3118
खारसी लिंक मोटर मार्ग (मार्ग सं0-21)
Ch. 0.000 - 24.750
24.750 6.000 27.50 20 Sep 31 Oct 6.000 6.00 100 14 Oct 14:43 Aditya Nath Thakur, Assistant Engineer Civil, TD Chakrata