Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 155.89 55.00 83.00 20 Sep 2025 31 Oct 2025 54.62 53.94 98.76 %
MDR 1 48.33 14.00 27.50 20 Sep 2025 31 Oct 2025 13.90 14.00 100.72 %
ODR 1 24.75 6.00 27.50 20 Sep 2025 31 Oct 2025 5.96 6.00 100.67 %
5 228.97 75.00 138.00 74.48 73.94 99.27 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Chakrata SH 5442 चकराता लाखामण्डल बर्नीगाड राज्य मार्ग [ Ch. 0.000 - 65.340] 65.340 46.000 55.00 20 Sep 31 Oct 45.680 44.94 98 25 Oct 16:58 pm Aditya Nath Thakur, Assistant Engineer Civil, TD Chakrata
2 TD Chakrata SH 5558 त्यूनी पुरोला नौगांव राज्य मार्ग [ Ch. 0.000 - 20.000] 20.000 0.000 0.00 20 Sep 31 Oct 0.000 - - 3
3 TD Chakrata SH 5452 दारागाड कथियान कांडा राज्य मार्ग [ Ch. 0.000 - 70.550] 70.550 9.000 28.00 20 Sep 31 Oct 8.940 9.00 101 17 Oct 10:51 am Jwala Datt Kandpal, Assistant Engineer Civil, TD Chakrata 5
4 TD Chakrata MDR 5627 पुरोड़ी रावना डामटा मोटर मार्ग [ Ch. 0.000 - 48.325] 48.325 14.000 27.50 20 Sep 31 Oct 13.900 14.00 101 17 Oct 10:45 am Aditya Nath Thakur, Assistant Engineer Civil, TD Chakrata
5 TD Chakrata ODR 3118 खारसी लिंक मोटर मार्ग (मार्ग सं0-21) [ Ch. 0.000 - 24.750] 24.750 6.000 27.50 20 Sep 31 Oct 5.960 6.00 101 14 Oct 14:25 pm Aditya Nath Thakur, Assistant Engineer Civil, TD Chakrata