PD Haridwar

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 4 60.00 36.00 42.00 20 Sep 2025 31 Oct 2025 36.00 36.00 100
MDR 5 56.50 19.50 38.00 20 Sep 2025 31 Oct 2025 19.50 19.50 100
ODR 5 28.64 25.50 30.00 20 Sep 2025 31 Oct 2025 25.50 25.50 100
Total 14 145.14 81.00 110.00 81.00 81.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Haridwar SH 5432
बहादराबाद धनौरी इमलीखेड़ा भगवानपुर गागल हेड़ी राज्य मार्ग
Ch. 0.000 - 4.000
4.000 2.000 7.00 20 Sep 31 Oct 2.000 2.00 100 03 Oct 10:06 Man Mohan Singh, Assistant Engineer Civil, PD Haridwar
2 PD Haridwar SH 5473
ज्वालापुर सराय एक्कड़ बहादरपुर जट अम्बूवाला धनपुरा राज्य मार्ग
Ch. 0.000 - 11.240
11.240 3.000 10.00 20 Sep 31 Oct 3.000 3.00 100 03 Oct 10:21 Satish Kumar, Assistant Engineer Civil, PD Haridwar 1
3 PD Haridwar SH 5517
पुराना दिल्ली नीतिपास राज्य मार्ग
Ch. 0.000 - 11.420
11.420 11.000 10.00 20 Sep 31 Oct 11.000 11.00 100 17 Oct 10:41 Ganesh Dutt, Assistant Engineer Civil, PD Haridwar 17
4 PD Haridwar SH 5539
रोशनाबाद कुडकावाला बिहारीगढ राज्य मार्ग
Ch. 0.000 - 33.335
33.335 20.000 15.00 20 Sep 31 Oct 20.000 20.00 100 03 Oct 10:07 Man Mohan Singh, Assistant Engineer Civil, PD Haridwar 1
5 PD Haridwar MDR 5600
पिरान कलियर सोहलपुर मुजाहिदपुर सत्तीवाला कुड़कावाला मोटर मार्ग
Ch. 6.000 - 19.100
13.100 4.000 8.00 20 Sep 31 Oct 4.000 4.00 100 03 Oct 10:12 Man Mohan Singh, Assistant Engineer Civil, PD Haridwar 1
6 PD Haridwar MDR 5601
फतेहपुर खेड़ी शिकोहपुर सिकरोडा बेलकी हद्दीवाला मोटर मार्ग
Ch. 0.000 - 24.400
24.400 3.000 15.00 20 Sep 31 Oct 3.000 3.00 100 17 Oct 10:31 Man Mohan Singh, Assistant Engineer Civil, PD Haridwar
7 PD Haridwar MDR 5603
बढेड़ी राजपुताना अलावलपुर मोटर मार्ग
Ch. 7.500 - 12.000
4.500 4.500 5.00 20 Sep 31 Oct 4.500 4.50 100 17 Oct 11:14 Ajeet Singh, Assistant Engineer Civil, PD Haridwar 5
8 PD Haridwar MDR 5604
सीतापुर जमालपुर कलां जियापोता मोटर मार्ग
Ch. 0.000 - 5.500
5.500 5.000 5.00 20 Sep 31 Oct 5.000 5.00 100 10 Oct 10:56 Satish Kumar, Assistant Engineer Civil, PD Haridwar
9 PD Haridwar MDR 7665
औरंगाबाद तेलीवाला मोटर मार्ग
Ch. 0.000 - 9.000
9.000 3.000 5.00 20 Sep 31 Oct 3.000 3.00 100 03 Oct 10:25 Man Mohan Singh, Assistant Engineer Civil, PD Haridwar
10 PD Haridwar ODR 3969
राष्ट्रीय मार्ग संख्या 58 से औद्योगिक क्षेत्र तक चार लेन मार्ग
Ch. 0.000 - 4.000
4.000 4.000 10.00 20 Sep 31 Oct 4.000 4.00 100 03 Oct 15:22 Kirti Vardhan Negi, Assistant Engineer Civil, PD Haridwar
11 PD Haridwar ODR 3973
रोहालकी सहदेवपुर बोडाहेड़ी मोटर मार्ग
Ch. 0.000 - 8.100
8.100 5.000 5.00 20 Sep 31 Oct 5.000 5.00 100 17 Oct 11:12 Ajeet Singh, Assistant Engineer Civil, PD Haridwar 12
12 PD Haridwar ODR 4067
रा० मा० -74 रसियाबगढ़ से पीली पड़ाव मोटर मार्ग
Ch. 0.000 - 6.000
6.000 6.000 5.00 20 Sep 31 Oct 6.000 6.00 100 10 Oct 11:16 Satish Kumar, Assistant Engineer Civil, PD Haridwar
13 PD Haridwar ODR 4107
बहादराबाद बाईपास के सापेक्ष बहादराबाद कस्बे के अन्तर्गत वर्तमान राष्ट्रीय राजमार्ग-58 का भाग
Ch. 0.000 - 3.540
3.540 3.500 5.00 20 Sep 31 Oct 3.500 3.50 100 17 Oct 10:33 Man Mohan Singh, Assistant Engineer Civil, PD Haridwar
14 PD Haridwar ODR 3946
ज्वालापुर-ललताराव-चण्डीघाट मार्ग
Ch. 0.000 - 7.000
7.000 7.000 5.00 20 Sep 31 Oct 7.000 7.00 100 17 Oct 10:41 Ganesh Dutt, Assistant Engineer Civil, PD Haridwar