All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 159.50 66.00 145.00 20 Sep 2025 31 Oct 2025 65.53 66.00 100.72 %
3 159.50 66.00 145.00 65.53 66.00 100.72 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Sahiya SH 5475 कालसी चकराता राज्य मार्ग [ Ch. 0.000 - 40.000] 40.000 15.000 10.00 20 Sep 31 Oct 14.890 15.00 101 07 Oct 18:31 pm Radhika Sharma, Assistant Engineer Civil, TD Sahiya 20
2 TD Sahiya SH 5466 हरिपुर इच्छाड़ी मीनस राज्य मार्ग [ Ch. 0.000 - 72.000] 72.000 28.000 110.00 20 Sep 31 Oct 27.800 28.00 101 18 Oct 13:33 pm Bhavya Kamboj, Assistant Engineer Civil, TD Sahiya 34
3 TD Sahiya SH 5542 सहिया क़्वानू मीनस राज्य मार्ग [ Ch. 0.000 - 47.500] 47.500 23.000 25.00 20 Sep 31 Oct 22.840 23.00 101 18 Oct 13:48 pm Mukesh Kumar, Assistant Engineer Civil, TD Sahiya 14