Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 159.50 66.00 145.00 20 Sep 2025 31 Oct 2025 66.00 66.00 100
Total 3 159.50 66.00 145.00 66.00 66.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 TD Sahiya SH 5475
कालसी चकराता राज्य मार्ग
Ch. 0.000 - 40.000
40.000 15.000 10.00 20 Sep 31 Oct 15.000 15.00 100 07 Oct 18:49 Radhika Sharma, Assistant Engineer Civil, TD Sahiya 20
2 TD Sahiya SH 5466
हरिपुर इच्छाड़ी मीनस राज्य मार्ग
Ch. 0.000 - 72.000
72.000 28.000 110.00 20 Sep 31 Oct 28.000 28.00 100 18 Oct 13:51 Bhavya Kamboj, Assistant Engineer Civil, TD Sahiya 34
3 TD Sahiya SH 5542
सहिया क़्वानू मीनस राज्य मार्ग
Ch. 0.000 - 47.500
47.500 23.000 25.00 20 Sep 31 Oct 23.000 23.00 100 18 Oct 14:06 Mukesh Kumar, Assistant Engineer Civil, TD Sahiya 19