NH Div Haldwani

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
NH 3 153.40 50.00 119.50 15 Sep 2025 31 Oct 2025 50.00 50.00 100
Total 3 153.40 50.00 119.50 50.00 50.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 NH Haldwani NH 5720
राष्ट्रीय मार्ग 74 के जक्शंन के निकट काशीपुर रामनगर धूमाकोट थैलीसैण त्रिपालीसैण पाबौ राष्ट्रीय मार्ग 119 के निकट बुआखाल तक राष्ट्रीय राजमार्ग
Ch. 0.000 - 63.000
63.000 22.000 12.00 20 Sep 15 Oct 22.000 22.00 100 10 Nov 05:52 Manoj Kumar Bhatt, Assistant Engineer Civil, NH Div Haldwani 7
2 NH Haldwani NH 5712
रामपुर रुद्रपुर हल्द्वानी नैनीताल राष्ट्रीय राजमार्ग
Ch. 89.100 - 124.000
34.900 15.000 107.50 15 Sep 31 Oct 15.000 15.00 100 17 Oct 07:48 Parmod Kumar Suyal, Assistant Engineer Civil, NH Div Haldwani 23
3 NH Haldwani NH 8701
ज्योलीकोट अल्मोड़ा कर्णप्रयाग राष्ट्रीय राजमार्ग
Ch. 0.000 - 55.500
55.500 13.000 0.00 15 Sep 31 Oct 13.000 13.00 100 03 Nov 16:52 Girija Kishore Pandey, Assistant Engineer Civil, NH Div Haldwani 5