All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
NH 3 140.78 25.00 0.00 20 Sep 2025 31 Oct 2025 24.82 25.00 100.73 %
3 140.78 25.00 0.00 24.82 25.00 100.73 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 NH Badkot NH 5716 राष्ट्रीय मार्ग 72 के जक्ंशन से हरर्बटपुर विकासनगर-कालसी-बड़कोट बैंण्ड़ -राष्ट्रीय मार्ग 94 तक राष्ट्रीय राजमार्ग [ Ch. 41.000 - 111.350] 70.350 12.000 0.00 20 Sep 31 Oct 11.920 12.00 101 12 Oct 14:19 pm Ashok Chauhan, Assistant Engineer Civil, PD New Tehri 3
2 NH Badkot NH 5713 ऋषिकेश धरासू बड्कोट फूल चट्टी (यमुनोत्री) राष्ट्रीय राजमार्ग [ Ch. 122.000 - 147.230] 25.230 5.000 0.00 20 Sep 31 Oct 4.960 5.00 101 16 Oct 18:14 pm Arvind Pratap Singh, Assistant Engineer Civil, NH Div Barkot
3 NH Badkot NH 9732 ऋषिकेश धरासू बड्कोट फूल चट्टी (यमुनोत्री) राष्ट्रीय राजमार्ग [ Ch. 172.230 - 217.430] 45.200 8.000 0.00 20 Sep 31 Oct 7.940 8.00 101 16 Oct 18:12 pm Dheeraj Gupta, Assistant Engineer Civil, NH Div Barkot 1