NH Div Barkot

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
NH 3 137.78 25.00 0.00 20 Sep 2025 31 Oct 2025 25.00 25.00 100
Total 3 137.78 25.00 0.00 25.00 25.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 NH Badkot NH 5716
राष्ट्रीय मार्ग 72 के जक्ंशन से हरर्बटपुर विकासनगर-कालसी-बड़कोट बैंण्ड़ -राष्ट्रीय मार्ग 94 तक राष्ट्रीय राजमार्ग
Ch. 44.000 - 111.350
67.350 12.000 0.00 20 Sep 31 Oct 12.000 12.00 100 12 Oct 14:37 Ashok Chauhan, Assistant Engineer Civil, PD New Tehri 3
2 NH Badkot NH 5713
ऋषिकेश धरासू बड्कोट फूल चट्टी (यमुनोत्री) राष्ट्रीय राजमार्ग
Ch. 122.000 - 147.230
25.230 5.000 0.00 20 Sep 31 Oct 5.000 5.00 100 16 Oct 18:32 Arvind Pratap Singh, Assistant Engineer Civil, NH Div Barkot
3 NH Badkot NH 9732
ऋषिकेश धरासू बड्कोट फूल चट्टी (यमुनोत्री) राष्ट्रीय राजमार्ग
Ch. 172.230 - 217.430
45.200 8.000 0.00 20 Sep 31 Oct 8.000 8.00 100 16 Oct 18:30 Dheeraj Gupta, Assistant Engineer Civil, NH Div Barkot 1