Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 128.00 61.00 91.00 20 Sep 2025 31 Oct 2025 61.00 64.00 104.92
MDR 1 4.99 5.00 7.00 20 Sep 2025 31 Oct 2025 5.00 5.00 100
ODR 3 19.75 14.00 35.00 20 Sep 2025 31 Oct 2025 14.00 14.00 100
Total 7 152.74 80.00 133.00 80.00 83.00 103.75

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Pauri SH 5519
पौड़ी देवप्रयाग गजा जाजल राज्य मार्ग
Ch. 0.000 - 49.000
49.000 24.000 38.00 20 Sep 31 Oct 24.000 24.00 100 13 Oct 12:31 Suresh Babu Pal, Assistant Engineer Civil, PD Pauri 34
2 PD Pauri SH 5554
टिहरी हिण्डोलाखाल देवप्रयाग व्यासघाट बिलखेत राज्य मार्ग
Ch. 57.000 - 89.000
32.000 11.000 20.00 20 Sep 31 Oct 11.000 14.00 127 30 Sep 13:25 Martunjay Sharma, Assistant Engineer Civil, PD Pauri
3 PD Pauri SH 5748
स्व0 श्री गीताराम पोखरियाल राज्य मार्ग (मरचूला सराईखेत बैजरो पोखडा सतपुली पौड़ी राज्य मार्ग )
Ch. 188.400 - 235.400
47.000 26.000 33.00 20 Sep 31 Oct 26.000 26.00 100 23 Oct 12:30 Firoz Ahamad, Assistant Engineer Civil, PD Pauri 1
4 PD Pauri MDR 4380
बेताल भौसाल मुण्डेश्वर कल्जीखाल मोटर मार्ग
Ch. 34.006 - 39.000
4.994 5.000 7.00 20 Sep 31 Oct 5.000 5.00 100 28 Oct 11:29 Firoz Ahamad, Assistant Engineer Civil, PD Pauri
5 PD Pauri ODR 4383
पिपला टेका मोटर मार्ग
Ch. 17.910 - 29.500
11.590 6.000 18.00 20 Sep 31 Oct 6.000 6.00 100 17 Nov 12:48 Archana, Assistant Engineer Civil, PD Pauri
6 PD Pauri ODR 4384
पथराड़ाखाल गेठीछेड़ा मोटर मार्ग
Ch. 13.345 - 18.000
4.655 5.000 10.00 20 Sep 31 Oct 5.000 5.00 100 19 Oct 11:23 Suresh Babu Pal, Assistant Engineer Civil, PD Pauri
7 PD Pauri ODR 4379
पौड़ी-खोलाचौरी
Ch. 0.000 - 3.500
3.500 3.000 7.00 20 Sep 31 Oct 3.000 3.00 100 13 Oct 12:27 Suresh Babu Pal, Assistant Engineer Civil, PD Pauri 13