Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 4 112.90 20.00 24.50 20 Sep 2025 31 Oct 2025 20.00 22.00 110.00 %
SH 1 32.22 4.00 9.60 20 Sep 2025 31 Oct 2025 4.00 4.00 100.00 %
ODR 1 22.00 4.00 9.00 20 Sep 2025 31 Oct 2025 4.00 4.00 100.00 %
6 167.12 28.00 43.10 28.00 30.00 107.14 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Srinagar MDR 5667 खण्डाह सुमाडी बुधाणी देवलगढ चमधार मोटर मार्ग [ Ch. 0.000 - 32.000] 32.000 6.000 5.00 20 Sep 31 Oct 6.000 8.00 133 08 Oct 09:20 am Kishore Kumar, Executive Engineer Civil, CD Srinagar
2 CD Srinagar SH 5488 पौड़ी खिर्सू खेडाखाल खांखरा राज्य मार्ग [ Ch. 0.000 - 32.220] 32.220 4.000 9.60 20 Sep 31 Oct 4.000 4.00 100 24 Sep 11:33 am Naresh Kumar, Assistant Engineer Civil, CD Srinagar 7
3 CD Srinagar MDR 4594 पौड़ी देहलचौरी उफल्डा मोटर मार्ग [ Ch. 6.000 - 31.650] 25.650 5.000 10.00 20 Sep 31 Oct 5.000 5.00 100 30 Sep 09:59 am Anil Kumar, Assistant Engineer Civil, CD Srinagar 7
4 CD Srinagar MDR 4592 उफल्डा खन्दुखाल मुछयाली चराकोट जामलाखाल घुरदोडी मोटर मार्ग [ Ch. 0.000 - 29.300] 29.300 2.000 5.00 20 Sep 31 Oct 2.000 2.00 100 04 Oct 09:56 am Anil Kumar, Assistant Engineer Civil, CD Srinagar
5 CD Srinagar MDR 5674 पौड़ी खिर्सू श्रीनगर मोटर मार्ग [ Ch. 0.000 - 25.950] 25.950 7.000 4.50 20 Sep 31 Oct 7.000 7.00 100 13 Oct 15:40 pm Harsh Bardhan, Assistant Engineer Civil, CD Srinagar
6 CD Srinagar ODR 4586 खिर्सू पिठुण्डी हरियाली आदीबद्री मोटर मार्ग [ Ch. 0.000 - 22.000] 22.000 4.000 9.00 20 Sep 31 Oct 4.000 4.00 100 16 Oct 11:42 am Naresh Kumar, Assistant Engineer Civil, CD Srinagar 2