CD Srinagar

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
MDR 4 112.90 20.00 24.50 20 Sep 2025 31 Oct 2025 20.00 22.00 110
SH 1 32.22 4.00 9.60 20 Sep 2025 31 Oct 2025 4.00 4.00 100
ODR 1 22.00 4.00 9.00 20 Sep 2025 31 Oct 2025 4.00 4.00 100
Total 6 167.12 28.00 43.10 28.00 30.00 107.14

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Srinagar MDR 5667
खण्डाह सुमाडी बुधाणी देवलगढ चमधार मोटर मार्ग
Ch. 0.000 - 32.000
32.000 6.000 5.00 20 Sep 31 Oct 6.000 8.00 133 08 Oct 09:38 Kishore Kumar, Executive Engineer Civil, CD Srinagar
2 CD Srinagar SH 5488
पौड़ी खिर्सू खेडाखाल खांखरा राज्य मार्ग
Ch. 0.000 - 32.220
32.220 4.000 9.60 20 Sep 31 Oct 4.000 4.00 100 24 Sep 11:51 Naresh Kumar, Assistant Engineer Civil, CD Srinagar 7
3 CD Srinagar MDR 4594
पौड़ी देहलचौरी उफल्डा मोटर मार्ग
Ch. 6.000 - 31.650
25.650 5.000 10.00 20 Sep 31 Oct 5.000 5.00 100 30 Sep 10:17 Anil Kumar, Assistant Engineer Civil, CD Srinagar 7
4 CD Srinagar MDR 4592
उफल्डा खन्दुखाल मुछयाली चराकोट जामलाखाल घुरदोडी मोटर मार्ग
Ch. 0.000 - 29.300
29.300 2.000 5.00 20 Sep 31 Oct 2.000 2.00 100 04 Oct 10:14 Anil Kumar, Assistant Engineer Civil, CD Srinagar
5 CD Srinagar MDR 5674
पौड़ी खिर्सू श्रीनगर मोटर मार्ग
Ch. 0.000 - 25.950
25.950 7.000 4.50 20 Sep 31 Oct 7.000 7.00 100 13 Oct 15:58 Harsh Bardhan, Assistant Engineer Civil, CD Srinagar
6 CD Srinagar ODR 4586
खिर्सू पिठुण्डी हरियाली आदीबद्री मोटर मार्ग
Ch. 0.000 - 22.000
22.000 4.000 9.00 20 Sep 31 Oct 4.000 4.00 100 16 Oct 12:00 Naresh Kumar, Assistant Engineer Civil, CD Srinagar 2