Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 1 155.10 18.00 40.00 20 Sep 2025 31 Oct 2025 18.00 18.00 100
MDR 1 92.00 27.00 55.00 20 Sep 2025 31 Oct 2025 27.00 27.00 100
Total 2 247.10 45.00 95.00 45.00 45.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Lansdown SH 5591
शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग )
Ch. 14.500 - 169.600
155.100 18.000 40.00 20 Sep 31 Oct 18.000 18.00 100 23 Oct 13:01 Vivek Kumar Singh, Executive Engineer Civil, PD Lansdown 1
2 PD Lansdown MDR 4661
सतपुली दुधारखाल धारकोट सिसल्डी मोटर मार्ग
Ch. 0.000 - 92.000
92.000 27.000 55.00 20 Sep 31 Oct 27.000 27.00 100 23 Oct 13:02 Vivek Kumar Singh, Executive Engineer Civil, PD Lansdown 2