All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 155.10 18.00 40.00 20 Sep 2025 31 Oct 2025 17.87 18.00 100.73 %
MDR 1 92.00 27.00 55.00 20 Sep 2025 31 Oct 2025 26.81 27.00 100.71 %
2 247.10 45.00 95.00 44.68 45.00 100.72 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Lansdown SH 5591 शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग ) [ Ch. 14.500 - 169.600] 155.100 18.000 40.00 20 Sep 31 Oct 17.870 18.00 101 23 Oct 12:43 pm Vivek Kumar Singh, Executive Engineer Civil, PD Lansdown 1
2 PD Lansdown MDR 4661 सतपुली दुधारखाल धारकोट सिसल्डी मोटर मार्ग [ Ch. 0.000 - 92.000] 92.000 27.000 55.00 20 Sep 31 Oct 26.810 27.00 101 23 Oct 12:44 pm Vivek Kumar Singh, Executive Engineer Civil, PD Lansdown 2