Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 2 93.00 24.00 60.00 20 Sep 2025 31 Oct 2025 23.83 24.00 100.71 %
SH 2 67.80 24.00 60.00 20 Sep 2025 31 Oct 2025 23.83 24.00 100.71 %
ODR 1 11.62 1.00 2.50 20 Sep 2025 31 Oct 2025 0.99 1.00 101.01 %
5 172.42 49.00 122.50 48.65 49.00 100.72 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Baijroo MDR 6186 मैठाणाघाट ढौंर जाखणी तकुलसारी रसियामहादेव सौंफखाल दिवोली बन्दरकोट नौलापुर मोटर मार्ग [ Ch. 0.000 - 41.000] 41.000 13.000 32.50 20 Sep 31 Oct 12.910 13.00 101 05 Oct 08:12 am Lokesh Kumar Saraswat, Executive Engineer Civil, CD Baijro 2
2 CD Baijroo SH 5593 शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग ) [ Ch. 169.600 - 187.400] 17.800 5.000 12.50 20 Sep 31 Oct 4.960 5.00 101 02 Oct 11:23 am Tasleem Ahamad, Assistant Engineer Civil, CD Baijro
3 CD Baijroo SH 5557 थलीसैंण बूंगीधार देघाट जैनल मानिला डोटियाल मरचूला राज्य मार्ग [ Ch. 0.000 - 50.000] 50.000 19.000 47.50 20 Sep 31 Oct 18.870 19.00 101 15 Oct 11:16 am Tasleem Ahamad, Assistant Engineer Civil, CD Baijro
4 CD Baijroo MDR 6185 बैजरो जोगमढ़ी सराईखेत भगवतीतलैया चौखाल जसपुर भण्डेली मोटर मार्ग [ Ch. 0.000 - 52.000] 52.000 11.000 27.50 20 Sep 31 Oct 10.920 11.00 101 23 Oct 19:41 pm Lokesh Kumar Saraswat, Executive Engineer Civil, CD Baijro
5 CD Baijroo ODR 4936 बेदीखाल भरोलीखाल एरोली मोटर मार्ग [ Ch. 0.000 - 11.620] 11.620 1.000 2.50 20 Sep 31 Oct 0.990 1.00 101 11 Oct 13:26 pm Lokesh Kumar Saraswat, Executive Engineer Civil, CD Baijro 1