CD Baijro

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
MDR 2 93.00 24.00 60.00 20 Sep 2025 31 Oct 2025 24.00 24.00 100
SH 2 67.80 24.00 60.00 20 Sep 2025 31 Oct 2025 24.00 24.00 100
ODR 1 11.62 1.00 2.50 20 Sep 2025 31 Oct 2025 1.00 1.00 100
Total 5 172.42 49.00 122.50 49.00 49.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Baijroo MDR 6186
मैठाणाघाट ढौंर जाखणी तकुलसारी रसियामहादेव सौंफखाल दिवोली बन्दरकोट नौलापुर मोटर मार्ग
Ch. 0.000 - 41.000
41.000 13.000 32.50 20 Sep 31 Oct 13.000 13.00 100 05 Oct 08:30 Lokesh Kumar Saraswat, Executive Engineer Civil, CD Baijro 2
2 CD Baijroo SH 5593
शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग )
Ch. 169.600 - 187.400
17.800 5.000 12.50 20 Sep 31 Oct 5.000 5.00 100 02 Oct 11:41 Tasleem Ahamad, Assistant Engineer Civil, CD Baijro
3 CD Baijroo SH 5557
थलीसैंण बूंगीधार देघाट जैनल मानिला डोटियाल मरचूला राज्य मार्ग
Ch. 0.000 - 50.000
50.000 19.000 47.50 20 Sep 31 Oct 19.000 19.00 100 15 Oct 11:34 Tasleem Ahamad, Assistant Engineer Civil, CD Baijro
4 CD Baijroo MDR 6185
बैजरो जोगमढ़ी सराईखेत भगवतीतलैया चौखाल जसपुर भण्डेली मोटर मार्ग
Ch. 0.000 - 52.000
52.000 11.000 27.50 20 Sep 31 Oct 11.000 11.00 100 23 Oct 19:59 Lokesh Kumar Saraswat, Executive Engineer Civil, CD Baijro
5 CD Baijroo ODR 4936
बेदीखाल भरोलीखाल एरोली मोटर मार्ग
Ch. 0.000 - 11.620
11.620 1.000 2.50 20 Sep 31 Oct 1.000 1.00 100 11 Oct 13:44 Lokesh Kumar Saraswat, Executive Engineer Civil, CD Baijro 1