Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 1 30.30 9.00 18.00 20 Sep 2025 31 Oct 2025 9.00 9.00 100
MDR 2 86.75 14.00 28.00 20 Sep 2025 31 Oct 2025 14.00 14.00 100
ODR 2 30.90 14.00 28.00 20 Sep 2025 31 Oct 2025 14.00 14.00 100
Total 5 147.95 37.00 74.00 37.00 37.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Paboo SH 5477
कर्णप्रयाग नौटी पैठाणी राज्य मार्ग
Ch. 47.150 - 77.450
30.300 9.000 18.00 20 Sep 31 Oct 9.000 9.00 100 11 Oct 09:12 Ashok Kumar, Assistant Engineer Civil, CD Pabo 14
2 CD Paboo MDR 5650
पाबौं संतुधार नौगांवखाल दमदवेल चौबट्टाखाल चौरीखाल मोटर मार्ग
Ch. 0.000 - 69.300
69.300 9.000 18.00 20 Sep 31 Oct 9.000 9.00 100 18 Oct 15:33 Anil Kumar, Assistant Engineer Civil, CD Pabo 2
3 CD Paboo MDR 4987
पैठाणी बडेथ नौडी मोटर मार्ग
Ch. 0.000 - 17.450
17.450 5.000 10.00 20 Sep 31 Oct 5.000 5.00 100 11 Oct 09:12 Ashok Kumar, Assistant Engineer Civil, CD Pabo 3
4 CD Paboo ODR 4968
चंगीन कुचौंली कुठूयूड मोटर मार्ग
Ch. 0.000 - 15.400
15.400 2.000 4.00 20 Sep 31 Oct 2.000 2.00 100 16 Oct 19:27 Shivam Mittal, Executive Engineer Civil, CD Srinagar 2
5 CD Paboo ODR 5044
गोड्ख्याखाल विशल्ड चोपड़िया मोटर मार्ग
Ch. 0.000 - 15.500
15.500 12.000 24.00 20 Sep 31 Oct 12.000 12.00 100 18 Oct 15:33 Anil Kumar, Assistant Engineer Civil, CD Pabo