Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 30.30 9.00 18.00 20 Sep 2025 31 Oct 2025 8.94 9.00 100.67 %
MDR 2 86.75 14.00 28.00 20 Sep 2025 31 Oct 2025 13.90 14.00 100.72 %
ODR 2 30.90 14.00 28.00 20 Sep 2025 31 Oct 2025 13.91 14.00 100.65 %
5 147.95 37.00 74.00 36.75 37.00 100.68 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Paboo SH 5477 कर्णप्रयाग नौटी पैठाणी राज्य मार्ग [ Ch. 47.150 - 77.450] 30.300 9.000 18.00 20 Sep 31 Oct 8.940 9.00 101 11 Oct 08:54 am Ashok Kumar, Assistant Engineer Civil, CD Pabo 14
2 CD Paboo MDR 5650 पाबौं संतुधार नौगांवखाल दमदवेल चौबट्टाखाल चौरीखाल मोटर मार्ग [ Ch. 0.000 - 69.300] 69.300 9.000 18.00 20 Sep 31 Oct 8.940 9.00 101 18 Oct 15:15 pm Anil Kumar, Assistant Engineer Civil, CD Pabo 2
3 CD Paboo MDR 4987 पैठाणी बडेथ नौडी मोटर मार्ग [ Ch. 0.000 - 17.450] 17.450 5.000 10.00 20 Sep 31 Oct 4.960 5.00 101 11 Oct 08:54 am Ashok Kumar, Assistant Engineer Civil, CD Pabo 3
4 CD Paboo ODR 4968 चंगीन कुचौंली कुठूयूड मोटर मार्ग [ Ch. 0.000 - 15.400] 15.400 2.000 4.00 20 Sep 31 Oct 1.990 2.00 101 16 Oct 19:09 pm Shivam Mittal, Executive Engineer Civil, CD Srinagar 2
5 CD Paboo ODR 5044 गोड्ख्याखाल विशल्ड चोपड़िया मोटर मार्ग [ Ch. 0.000 - 15.500] 15.500 12.000 24.00 20 Sep 31 Oct 11.920 12.00 101 18 Oct 15:15 pm Anil Kumar, Assistant Engineer Civil, CD Pabo