Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 1 40.25 11.00 12.00 20 Sep 2025 31 Oct 2025 11.00 11.00 100
MDR 2 30.00 14.00 21.00 20 Sep 2025 31 Oct 2025 14.00 14.00 100
Total 3 70.25 25.00 33.00 25.00 25.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Gairsain SH 5439
भिक्यासैण देघाट बूंगीधार मैहलचौरी बच्छुवाबाण चौखुटिया राज्य मार्ग
Ch. 73.775 - 114.025
40.250 11.000 12.00 20 Sep 31 Oct 11.000 11.00 100 16 Oct 16:22 Sandesh Uniyal, Assistant Engineer Civil, CD Gairsain 9
2 CD Gairsain MDR 5058
बूंगीधार मैहलचौरी बच्छुवाबाण तलवाडी मोटर मार्ग
Ch. 0.000 - 14.000
14.000 9.000 18.00 20 Sep 31 Oct 9.000 9.00 100 16 Oct 09:56 Sandesh Uniyal, Assistant Engineer Civil, CD Gairsain 1
3 CD Gairsain MDR 5059
पाण्डुवाखाल रोहिडा पंजियाणा मोटर मार्ग
Ch. 0.000 - 16.000
16.000 5.000 3.00 20 Sep 31 Oct 5.000 5.00 100 16 Oct 10:24 Alok Hatwal, Assistant Engineer Civil, CD Gairsain 1