Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 40.25 11.00 12.00 20 Sep 2025 31 Oct 2025 10.92 11.00 100.73 %
MDR 2 30.00 14.00 21.00 20 Sep 2025 31 Oct 2025 13.90 14.00 100.72 %
3 70.25 25.00 33.00 24.82 25.00 100.73 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Gairsain SH 5439 भिक्यासैण देघाट बूंगीधार मैहलचौरी बच्छुवाबाण चौखुटिया राज्य मार्ग [ Ch. 73.775 - 114.025] 40.250 11.000 12.00 20 Sep 31 Oct 10.920 11.00 101 16 Oct 16:04 pm Sandesh Uniyal, Assistant Engineer Civil, CD Gairsain 9
2 CD Gairsain MDR 5058 बूंगीधार मैहलचौरी बच्छुवाबाण तलवाडी मोटर मार्ग [ Ch. 0.000 - 14.000] 14.000 9.000 18.00 20 Sep 31 Oct 8.940 9.00 101 16 Oct 09:38 am Sandesh Uniyal, Assistant Engineer Civil, CD Gairsain 1
3 CD Gairsain MDR 5059 पाण्डुवाखाल रोहिडा पंजियाणा मोटर मार्ग [ Ch. 0.000 - 16.000] 16.000 5.000 3.00 20 Sep 31 Oct 4.960 5.00 101 16 Oct 10:06 am Alok Hatwal, Assistant Engineer Civil, CD Gairsain 1