Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 78.13 16.00 40.00 20 Sep 2025 31 Oct 2025 15.88 16.00 100.76 %
MDR 1 16.00 7.00 8.00 20 Sep 2025 31 Oct 2025 6.95 5.00 71.94 %
ODR 3 16.55 16.55 21.25 20 Sep 2025 31 Oct 2025 16.43 13.85 84.30 %
6 110.68 39.55 69.25 39.26 34.85 88.77 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Pokhari SH 7838 रुद्रप्रयाग पोखरी गोपेश्वर राज्य मार्ग [ Ch. 35.000 - 87.320] 52.320 11.000 22.00 20 Sep 31 Oct 10.920 11.00 101 16 Oct 16:50 pm Mohammad Tasdeeq Uddin, Assistant Engineer Civil, CD Pokhari 12
2 CD Pokhari SH 5679 कर्णप्रयाग पोखरी गोपेश्वर राज्य मार्ग [ Ch. 0.000 - 25.810] 25.810 5.000 18.00 20 Sep 31 Oct 4.960 5.00 101 27 Sep 10:05 am Mohammad Tasdeeq Uddin, Assistant Engineer Civil, CD Pokhari 11
3 CD Pokhari MDR 5086 पोखरी विशालखाल आली कांडई मोटर मार्ग [ Ch. 0.000 - 16.000] 16.000 7.000 8.00 20 Sep 31 Oct 6.950 5.00 72 23 Oct 12:42 pm Mohammad Tasdeeq Uddin, Assistant Engineer Civil, CD Pokhari 9
4 CD Pokhari ODR 5085 पोखरी बाजार लिंक मोटर मार्ग [ Ch. 0.000 - 0.500] 0.500 0.500 1.00 20 Sep 31 Oct 0.500 0.50 100 30 Sep 16:49 pm Mohammad Tasdeeq Uddin, Assistant Engineer Civil, CD Pokhari 8
5 CD Pokhari ODR 5099 पोखरी हरिशंकर मोटर मार्ग [ Ch. 0.000 - 9.350] 9.350 9.350 11.50 20 Sep 31 Oct 9.280 9.35 101 12 Oct 09:50 am Mohammad Tasdeeq Uddin, Assistant Engineer Civil, CD Pokhari 16
6 CD Pokhari ODR 5083 जौरासी हापला कलसीर धोतीधार मोटर मार्ग [ Ch. 0.000 - 6.700] 6.700 6.700 8.75 20 Sep 31 Oct 6.650 4.00 60 23 Oct 12:42 pm Mohammad Tasdeeq Uddin, Assistant Engineer Civil, CD Pokhari