CD Laksar

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 4 49.96 39.96 59.00 20 Sep 2025 31 Oct 2025 39.96 39.96 100
MDR 1 8.30 8.00 28.00 20 Sep 2025 31 Oct 2025 8.00 8.00 100
ODR 1 6.00 3.00 9.00 20 Sep 2025 31 Oct 2025 3.00 3.50 116.67
Total 6 64.26 50.96 96.00 50.96 51.46 100.98

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Laksar SH 5573
रुड़की लण्ढौरा लक्सर बालावाली राज्य मार्ग
Ch. 9.000 - 18.300
9.300 9.300 15.00 20 Sep 31 Oct 9.300 9.30 100 03 Oct 08:59 Lalit Mohan Singh, Assistant Engineer Civil, CD Laksar
2 CD Laksar SH 7633
रुड़की लण्ढौरा लक्सर बालावाली राज्य मार्ग
Ch. 19.000 - 35.000
16.000 16.000 10.00 20 Sep 31 Oct 16.000 16.00 100 18 Oct 13:05 Anil Kumar, Assistant Engineer Civil, CD Laksar
3 CD Laksar SH 5540
शाहपुर भोगपुर निरंजनपुर रायसी राज्य मार्ग
Ch. 7.000 - 21.657
14.657 14.657 34.00 20 Sep 31 Oct 14.657 14.66 100 24 Oct 09:30 Anil Kumar, Assistant Engineer Civil, CD Laksar 1
4 CD Laksar MDR 5678
खानपुर दल्लावाला मोटर मार्ग
Ch. 0.000 - 8.300
8.300 8.000 28.00 20 Sep 31 Oct 8.000 8.00 100 23 Sep 11:36 Anil Kumar, Assistant Engineer Civil, CD Laksar 4
5 CD Laksar ODR 7926
मंगलौर-लंढौरा मार्ग
Ch. 0.000 - 6.000
6.000 3.000 9.00 20 Sep 31 Oct 3.000 3.50 117 24 Oct 10:53 Anil Kumar, Assistant Engineer Civil, CD Laksar 5
6 CD Laksar SH 5471
ज्वालापुर सराय सुभाषगढ़ ऐथल बसेड़ी खादर राज्य मार्ग
Ch. 11.000 - 21.000
10.000 0.000 0.00 20 Sep 31 Oct 0.000 - 0