Loading Dashboard...

Back

NH Div Rudraprayag

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
NH 4 229.20 80.00 35.00 20 Sep 2025 31 Oct 2025 80.00 81.00 101.25
Total 4 229.20 80.00 35.00 80.00 81.00 101.25

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 NH Rudraprayag NH 8683
दिल्ली गाजियाबाद बद्रीनाथ माणा राष्ट्रीय राजमार्ग
Ch. 350.000 - 355.000
5.000 4.000 0.00 20 Sep 31 Oct 4.000 5.00 125 13 Oct 16:00 Sourabh Dhoundiyal, Assistant Engineer Civil, NH Div Rudraprayag 17
2 NH Rudraprayag NH 5714
रुद्रप्रयाग गोरीकुंड राष्ट्रीय राजमार्ग
Ch. 0.000 - 76.000
76.000 28.000 0.00 20 Sep 31 Oct 28.000 28.00 100 23 Oct 13:45 Sourabh Dhoundiyal, Assistant Engineer Civil, NH Div Rudraprayag 1
3 NH Rudraprayag NH 5727
गोपेश्वर ऊखीमठ बरमवारी राष्ट्रीय राजमार्ग
Ch. 0.000 - 84.200
84.200 26.000 20.00 20 Sep 31 Oct 26.000 26.00 100 23 Oct 13:45 Sourabh Dhoundiyal, Assistant Engineer Civil, NH Div Rudraprayag
4 NH Rudraprayag NH 5721
ज्योलीकोट अल्मोड़ा कर्णप्रयाग राष्ट्रीय राजमार्ग
Ch. 171.000 - 235.000
64.000 22.000 15.00 20 Sep 31 Oct 22.000 22.00 100 15 Oct 21:19 Prerna Jagoori, Assistant Engineer Civil, NH Div Rudraprayag