Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | NH Doiwala | NH | 5710 |
अम्बाला पौंटा साहिब देहरादून ऋषिकेश (हरिद्वार) राष्ट्रीय राजमार्ग
Ch. 148.000 - 165.000
|
17.000 | 4.000 | 35.00 | 20 Sep | 25 Oct | 4.000 | 4.00 | 100 | 16 Oct 18:00 | Anil Kumar Singh Bisht, Assistant Engineer Civil, NH Div Doiwala | |
| 2 | NH Doiwala | NH | 5708 |
दिल्ली गाजियाबाद बद्रीनाथ माणा राष्ट्रीय राजमार्ग
Ch. 218.200 - 228.200
|
10.000 | 4.000 | 20.00 | 20 Sep | 31 Oct | 4.000 | 4.00 | 100 | 16 Oct 17:32 | Vijay Kumar, Assistant Engineer Civil, NH Div Doiwala |