NH Div Lohaghat

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
NH 2 242.80 51.00 90.00 20 Sep 2025 31 Oct 2025 51.00 54.00 105.88
Total 2 242.80 51.00 90.00 51.00 54.00 105.88

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 NH Lohaghat NH 5724
राष्ट्रीय मार्ग 74 के जंक्शन सितारगंज-खटीमा-टनकपुर-पिथौरागढ राष्ट्रीय राजमार्ग
Ch. 52.880 - 202.680
149.800 47.000 80.00 20 Sep 31 Oct 47.000 51.00 109 17 Oct 07:46 Dan Singh, Assistant Engineer Civil, NH Div Lohaghat 2
2 NH Lohaghat NH 5728
घाट गंगोलीहाट बेरीनाग चैकोड़ी कांडा बागेश्वर ताकुला अल्मोड़ा राष्ट्रीय राजमार्ग
Ch. 0.000 - 93.000
93.000 4.000 10.00 20 Sep 31 Oct 4.000 3.00 75 30 Sep 16:51 Dan Singh, Assistant Engineer Civil, NH Div Lohaghat