Work Sanctioned
राज्य योजना के अंतर्गत जनपद नैनीताल के विकासखंड रामगढ़ के अंतर्गत पी० एम ० जी ० एस ० वाई ० से हस्तान्तरित शीतला -.छतौला मोटर मार्ग में आवश्यक विशेष मरम्मत एवं अनुरक्षण का कार्य।
on Wednesday, May 17th 2023, 7:43:51 am
Technical Sanction
of ₹ 142.54 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1312/36C
on Thursday, September 7th 2023, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, September 27th 2023, 9:29:14 am
PWD UttarakahndPhoto (ID 24264) from Site Received
Uploader : Manmohan Singh, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : 0.150
Remark : Hill side cutting
on Wednesday, October 4th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, October 11th 2023, 10:12:15 am
PWD UttarakahndPhoto (ID 24827) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 6
Remark : Work in progress
on Wednesday, October 11th 2023, 10:15:01 am
PWD UttarakahndPhoto (ID 24828) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 6
Remark : Work in progress
on Wednesday, October 11th 2023, 10:23:39 am
PWD UttarakahndPhoto (ID 24831) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 5
Remark : R/wall Construction in progress
on Saturday, October 14th 2023, 9:01:28 am
PWD UttarakahndPhoto (ID 25083) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 3
Remark : Construction of R/wall
on Tuesday, October 31st 2023, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, November 2nd 2023, 6:30:00 pm
15.90%
Financial Progress
1st Expenditure
of ₹ 2265745 (22.66 Lacs ) done.
Cummulative ₹ 22.66Lacs ( against 142.54Lacs )
on Thursday, December 14th 2023, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, January 3rd 2024, 6:54:16 am
PWD UttarakahndPhoto (ID 34179) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 2
Remark : Construction of R wall
on Wednesday, January 3rd 2024, 7:04:25 am
PWD UttarakahndPhoto (ID 34180) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 3
Remark : Construction of R wall
on Wednesday, January 3rd 2024, 7:10:52 am
PWD UttarakahndPhoto (ID 34181) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 3
Remark : Construction of R wall
on Wednesday, January 3rd 2024, 7:12:41 am
PWD UttarakahndPhoto (ID 34182) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 4
Remark : Construction of R wall
on Wednesday, January 31st 2024, 8:05:41 am
PWD UttarakahndPhoto (ID 35421) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Km 1(0-2)
Remark : Work in progress
on Friday, February 23rd 2024, 10:24:04 am
PWD UttarakahndPhoto (ID 36194) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Construction of parafit
on Friday, February 23rd 2024, 10:26:10 am
PWD UttarakahndPhoto (ID 36195) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km1
Remark : Construction of parapit
on Wednesday, March 6th 2024, 6:30:00 pm
56.20%
Financial Progress
2nd Expenditure
of ₹ 5745631 (57.46 Lacs ) done.
Cummulative ₹ 80.11Lacs ( against 142.54Lacs )
on Tuesday, April 16th 2024, 8:18:08 am
PWD UttarakahndPhoto (ID 37473) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Pc work
on Tuesday, April 16th 2024, 8:20:22 am
PWD UttarakahndPhoto (ID 37475) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Pc work
on Tuesday, April 23rd 2024, 9:56:43 am
PWD UttarakahndPhoto (ID 37646) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Pc work
on Saturday, April 27th 2024, 10:12:47 am
PWD UttarakahndPhoto (ID 37657) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km2
Remark : Pc work
on Thursday, May 2nd 2024, 7:19:59 am
PWD UttarakahndPhoto (ID 37780) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 2
Remark : P c work in progress
on Tuesday, May 28th 2024, 6:30:00 pm
77.25%
Financial Progress
3rd Expenditure
of ₹ 3000000 (30.00 Lacs ) done.
Cummulative ₹ 110.11Lacs ( against 142.54Lacs )
on Friday, June 14th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Thursday, July 25th 2024, 6:30:00 pm
83.18%
Financial Progress
4th Expenditure
of ₹ 845133 (8.45 Lacs ) done.
Cummulative ₹ 118.57Lacs ( against 142.54Lacs )