2 years ago

on Monday, May 15th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अंतर्गत जनपद नैनीताल के विकासखंड रामगढ़ के अंतर्गत पी० एम ० जी ० एस ० वाई ० से हस्तान्तरित शीतला -.छतौला मोटर मार्ग में आवश्यक विशेष मरम्मत एवं अनुरक्षण का कार्य।

2 years ago

on Wednesday, May 17th 2023, 7:43:51 am

Technical Sanction
of ₹ 142.54 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1312/36C

2 years ago

on Thursday, September 7th 2023, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Wednesday, September 27th 2023, 9:29:14 am
<span class="4">Picture Id:24264</span>
PWD Uttarakahnd
Photo (ID 24264) from Site Received
Uploader : Manmohan Singh, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : 0.150
Remark : Hill side cutting

2 years ago

on Wednesday, October 4th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Wednesday, October 11th 2023, 10:12:15 am
<span class="4">Picture Id:24827</span>
PWD Uttarakahnd
Photo (ID 24827) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 6
Remark : Work in progress

2 years ago

on Wednesday, October 11th 2023, 10:15:01 am
<span class="4">Picture Id:24828</span>
PWD Uttarakahnd
Photo (ID 24828) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 6
Remark : Work in progress

2 years ago

on Wednesday, October 11th 2023, 10:23:39 am
<span class="4">Picture Id:24831</span>
PWD Uttarakahnd
Photo (ID 24831) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 5
Remark : R/wall Construction in progress

2 years ago

on Saturday, October 14th 2023, 9:01:28 am
<span class="4">Picture Id:25083</span>
PWD Uttarakahnd
Photo (ID 25083) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 3
Remark : Construction of R/wall

2 years ago

on Tuesday, October 31st 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Thursday, November 2nd 2023, 6:30:00 pm
15.90%
Financial Progress

1st Expenditure
of ₹ 2265745 (22.66 Lacs ) done.
Cummulative ₹ 22.66Lacs ( against 142.54Lacs )

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Wednesday, January 3rd 2024, 6:54:16 am
<span class="4">Picture Id:34179</span>
PWD Uttarakahnd
Photo (ID 34179) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 2
Remark : Construction of R wall

2 years ago

on Wednesday, January 3rd 2024, 7:04:25 am
<span class="4">Picture Id:34180</span>
PWD Uttarakahnd
Photo (ID 34180) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 3
Remark : Construction of R wall

2 years ago

on Wednesday, January 3rd 2024, 7:10:52 am
<span class="4">Picture Id:34181</span>
PWD Uttarakahnd
Photo (ID 34181) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 3
Remark : Construction of R wall

2 years ago

on Wednesday, January 3rd 2024, 7:12:41 am
<span class="4">Picture Id:34182</span>
PWD Uttarakahnd
Photo (ID 34182) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 4
Remark : Construction of R wall

2 years ago

on Wednesday, January 31st 2024, 8:05:41 am
<span class="4">Picture Id:35421</span>
PWD Uttarakahnd
Photo (ID 35421) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Km 1(0-2)
Remark : Work in progress

2 years ago

on Friday, February 23rd 2024, 10:24:04 am
<span class="4">Picture Id:36194</span>
PWD Uttarakahnd
Photo (ID 36194) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Construction of parafit

2 years ago

on Friday, February 23rd 2024, 10:26:10 am
<span class="4">Picture Id:36195</span>
PWD Uttarakahnd
Photo (ID 36195) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km1
Remark : Construction of parapit

2 years ago

on Wednesday, March 6th 2024, 6:30:00 pm
56.20%
Financial Progress

2nd Expenditure
of ₹ 5745631 (57.46 Lacs ) done.
Cummulative ₹ 80.11Lacs ( against 142.54Lacs )

a year ago

on Tuesday, April 16th 2024, 8:18:08 am
<span class="4">Picture Id:37473</span>
PWD Uttarakahnd
Photo (ID 37473) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Pc work

a year ago

on Tuesday, April 16th 2024, 8:20:22 am
<span class="4">Picture Id:37475</span>
PWD Uttarakahnd
Photo (ID 37475) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Pc work

a year ago

on Tuesday, April 23rd 2024, 9:56:43 am
<span class="4">Picture Id:37646</span>
PWD Uttarakahnd
Photo (ID 37646) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km 1
Remark : Pc work

a year ago

on Saturday, April 27th 2024, 10:12:47 am
<span class="4">Picture Id:37657</span>
PWD Uttarakahnd
Photo (ID 37657) from Site Received
Uploader : Rakesh Chandra Arya, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : Km2
Remark : Pc work

a year ago

on Thursday, May 2nd 2024, 7:19:59 am
<span class="4">Picture Id:37780</span>
PWD Uttarakahnd
Photo (ID 37780) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 2
Remark : P c work in progress

a year ago

on Tuesday, May 28th 2024, 6:30:00 pm
77.25%
Financial Progress

3rd Expenditure
of ₹ 3000000 (30.00 Lacs ) done.
Cummulative ₹ 110.11Lacs ( against 142.54Lacs )

a year ago

on Friday, June 14th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Thursday, July 25th 2024, 6:30:00 pm
83.18%
Financial Progress

4th Expenditure
of ₹ 845133 (8.45 Lacs ) done.
Cummulative ₹ 118.57Lacs ( against 142.54Lacs )