Work Sanctioned
सड़क सुरक्षा के अन्तर्गत चमड़िया छियोड़ी धुरा (ओडीआर) मोटर मार्ग के कि0मी0 1 से 15.30 के मध्य प्रस्तावित सड़क सुरक्षा कार्य।
on Wednesday, November 1st 2023, 10:36:13 am
Technical Sanction
of ₹ 73.42 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2642/36C dt. 01-11-2023
on Thursday, December 21st 2023, 10:38:54 am
PWD UttarakahndPhoto (ID 35287) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 12
Remark : Thickness 5 mm wide 150 mm found o k
on Saturday, January 27th 2024, 10:21:01 am
PWD UttarakahndPhoto (ID 35288) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 12
Remark : Length of post 2 m found ok
on Saturday, January 27th 2024, 10:23:26 am
PWD UttarakahndPhoto (ID 35289) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 12
Remark : Work starts
on Saturday, January 27th 2024, 10:42:30 am
PWD UttarakahndPhoto (ID 35293) from Site Received
Uploader : Manmohan Singh, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : 7.00
Remark : Crash barrier work
on Saturday, February 17th 2024, 7:40:14 am
PWD UttarakahndPhoto (ID 35993) from Site Received
Uploader : Manmohan Singh, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : 10.00
Remark : Road sath work
on Saturday, February 17th 2024, 9:50:04 am
PWD UttarakahndPhoto (ID 36008) from Site Received
Uploader : Manmohan Singh, Additional Assistant Engineer Civil ,CD Ranikhet
Landmark : 37
Remark : Road sath work
on Sunday, February 18th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 73.42Lacs )
on Sunday, February 18th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, February 28th 2024, 6:30:00 pm
100.00%
Financial Progress
2nd Expenditure
of ₹ 7342041 (73.42 Lacs ) done.
Cummulative ₹ 73.42Lacs ( against 73.42Lacs )
on Tuesday, June 4th 2024, 8:18:20 am
PWD UttarakahndPhoto (ID 41297) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 6
Remark : Road safety work progess