Work Sanctioned
जनपद नैनीताल के विकास खण्ड रामनगर के अन्तर्गत रिंग रोड से सक्खनपुर होकर एन0 एच0 121 तक पुनः निर्माण एवं सुधारीकरण का कार्य।
on Tuesday, February 28th 2017, 6:30:00 pm
0.01%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 700.54Lacs )
on Monday, July 31st 2017, 6:30:00 pm
0.00%
Financial Progress
2nd Expenditure
of ₹ -10000 (-0.10 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 700.54Lacs )
on Tuesday, October 31st 2017, 6:30:00 pm
Technical Sanction
of ₹ 700.54 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 10/2017-18
on Tuesday, October 31st 2017, 6:30:00 pm
0.01%
Financial Progress
3rd Expenditure
of ₹ 5250 (0.05 Lacs ) done.
Cummulative ₹ 0.05Lacs ( against 700.54Lacs )
on Monday, April 30th 2018, 6:30:00 pm
5.00%
Financial Progress
4th Expenditure
of ₹ 3500000 (35.00 Lacs ) done.
Cummulative ₹ 35.05Lacs ( against 700.54Lacs )
on Saturday, June 30th 2018, 6:30:00 pm
5.07%
Financial Progress
5th Expenditure
of ₹ 49391 (0.49 Lacs ) done.
Cummulative ₹ 35.55Lacs ( against 700.54Lacs )
on Tuesday, July 31st 2018, 6:30:00 pm
5.54%
Financial Progress
6th Expenditure
of ₹ 326593 (3.27 Lacs ) done.
Cummulative ₹ 38.81Lacs ( against 700.54Lacs )
on Friday, August 31st 2018, 6:30:00 pm
19.06%
Financial Progress
7th Expenditure
of ₹ 9470212 (94.70 Lacs ) done.
Cummulative ₹ 133.51Lacs ( against 700.54Lacs )
on Sunday, September 30th 2018, 6:30:00 pm
19.15%
Financial Progress
8th Expenditure
of ₹ 65890 (0.66 Lacs ) done.
Cummulative ₹ 134.17Lacs ( against 700.54Lacs )
on Wednesday, October 31st 2018, 6:30:00 pm
20.36%
Financial Progress
9th Expenditure
of ₹ 845365 (8.45 Lacs ) done.
Cummulative ₹ 142.63Lacs ( against 700.54Lacs )
on Friday, November 30th 2018, 6:30:00 pm
20.66%
Financial Progress
10th Expenditure
of ₹ 207000 (2.07 Lacs ) done.
Cummulative ₹ 144.70Lacs ( against 700.54Lacs )
on Monday, December 31st 2018, 6:30:00 pm
20.39%
Financial Progress
11th Expenditure
of ₹ -186300 (-1.86 Lacs ) done.
Cummulative ₹ 142.83Lacs ( against 700.54Lacs )
on Thursday, February 28th 2019, 6:30:00 pm
20.46%
Financial Progress
12th Expenditure
of ₹ 47350 (0.47 Lacs ) done.
Cummulative ₹ 143.31Lacs ( against 700.54Lacs )
on Saturday, August 31st 2019, 6:30:00 pm
23.89%
Financial Progress
13th Expenditure
of ₹ 2402485 (24.02 Lacs ) done.
Cummulative ₹ 167.33Lacs ( against 700.54Lacs )
on Thursday, October 31st 2019, 6:30:00 pm
35.50%
Financial Progress
14th Expenditure
of ₹ 8133374 (81.33 Lacs ) done.
Cummulative ₹ 248.67Lacs ( against 700.54Lacs )
on Saturday, February 29th 2020, 6:30:00 pm
46.68%
Financial Progress
15th Expenditure
of ₹ 7837879 (78.38 Lacs ) done.
Cummulative ₹ 327.04Lacs ( against 700.54Lacs )
on Sunday, May 31st 2020, 6:30:00 pm
47.33%
Financial Progress
16th Expenditure
of ₹ 449715 (4.50 Lacs ) done.
Cummulative ₹ 331.54Lacs ( against 700.54Lacs )
on Tuesday, June 30th 2020, 6:30:00 pm
47.54%
Financial Progress
17th Expenditure
of ₹ 148955 (1.49 Lacs ) done.
Cummulative ₹ 333.03Lacs ( against 700.54Lacs )
on Friday, July 31st 2020, 6:30:00 pm
47.61%
Financial Progress
18th Expenditure
of ₹ 49390 (0.49 Lacs ) done.
Cummulative ₹ 333.53Lacs ( against 700.54Lacs )
on Monday, August 31st 2020, 6:30:00 pm
47.62%
Financial Progress
19th Expenditure
of ₹ 3908 (0.04 Lacs ) done.
Cummulative ₹ 333.56Lacs ( against 700.54Lacs )
on Wednesday, September 30th 2020, 6:30:00 pm
47.62%
Financial Progress
20th Expenditure
of ₹ 1500 (0.01 Lacs ) done.
Cummulative ₹ 333.58Lacs ( against 700.54Lacs )
on Thursday, December 31st 2020, 6:30:00 pm
49.04%
Financial Progress
21st Expenditure
of ₹ 993242 (9.93 Lacs ) done.
Cummulative ₹ 343.51Lacs ( against 700.54Lacs )
on Sunday, January 31st 2021, 6:30:00 pm
49.93%
Financial Progress
22nd Expenditure
of ₹ 626552 (6.27 Lacs ) done.
Cummulative ₹ 349.78Lacs ( against 700.54Lacs )
on Wednesday, June 30th 2021, 6:30:00 pm
49%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, July 25th 2021, 6:30:00 pm
50.37%
Financial Progress
23rd Expenditure
of ₹ 305524 (3.06 Lacs ) done.
Cummulative ₹ 352.83Lacs ( against 700.54Lacs )
on Tuesday, August 24th 2021, 6:30:00 pm
50.55%
Financial Progress
24th Expenditure
of ₹ 126527 (1.27 Lacs ) done.
Cummulative ₹ 354.10Lacs ( against 700.54Lacs )
on Sunday, September 26th 2021, 6:30:00 pm
50.57%
Financial Progress
25th Expenditure
of ₹ 14400 (0.14 Lacs ) done.
Cummulative ₹ 354.24Lacs ( against 700.54Lacs )
on Friday, December 31st 2021, 6:30:00 pm
50.70%
Financial Progress
26th Expenditure
of ₹ 91582 (0.92 Lacs ) done.
Cummulative ₹ 355.16Lacs ( against 700.54Lacs )
on Wednesday, August 31st 2022, 8:23:14 am
PWD UttarakahndPhoto (ID 7625) from Site Received
Uploader : Neha Sharma, Assistant Engineer Civil ,CD Ramnagar
Landmark : 0.00
Remark : 60 percent work completed, Rest work obstructed due to court case.
on Wednesday, August 31st 2022, 9:00:24 am
PWD UttarakahndPhoto (ID 7624) from Site Received
Uploader : Neha Sharma, Assistant Engineer Civil ,CD Ramnagar
Landmark : 5.995
Remark : 60 percent work completed, Rest work obstructed due to court case.
on Tuesday, December 6th 2022, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, January 19th 2023, 6:30:00 pm
50.77%
Financial Progress
27th Expenditure
of ₹ 49442 (0.49 Lacs ) done.
Cummulative ₹ 355.65Lacs ( against 700.54Lacs )
on Sunday, January 29th 2023, 6:30:00 pm
54.51%
Financial Progress
28th Expenditure
of ₹ 2620775 (26.21 Lacs ) done.
Cummulative ₹ 381.86Lacs ( against 700.54Lacs )
on Monday, July 31st 2023, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, August 1st 2023, 6:30:00 pm
67%
Physical Progress
Physical Progress Reported at 4th time