on Tuesday, December 14th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधान सभा क्षेत्र रामनगर में ललितपुर से बेरिया मोटर मार्ग का पी0सी0 द्वारा सुधारीकरण का कार्य।
on Tuesday, March 8th 2022, 6:30:00 pm
0.27%
Financial Progress
1st Expenditure
of ₹ 6490 (0.06 Lacs ) done.
Cummulative ₹ 0.06Lacs ( against 24.1Lacs )
on Sunday, March 27th 2022, 6:30:00 pm
0.69%
Financial Progress
2nd Expenditure
of ₹ 10148 (0.10 Lacs ) done.
Cummulative ₹ 0.17Lacs ( against 24.1Lacs )
on Tuesday, June 21st 2022, 5:07:15 am
PWD UttarakahndPhoto (ID 6163) from Site Received
Uploader : Neha Sharma, Assistant Engineer Civil ,CD Ramnagar
Landmark : 0.450
Remark : PC work
on Tuesday, July 26th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, September 15th 2022, 6:30:00 pm
71.83%
Financial Progress
3rd Expenditure
of ₹ 1714542 (17.15 Lacs ) done.
Cummulative ₹ 17.31Lacs ( against 24.1Lacs )
on Thursday, March 23rd 2023, 6:30:00 pm
77.71%
Financial Progress
4th Expenditure
of ₹ 141600 (1.42 Lacs ) done.
Cummulative ₹ 18.73Lacs ( against 24.1Lacs )