2 years ago

on Monday, September 11th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधान सभा क्षेत्र रामनगर में ग्राम भवानीपुर खुल्बे में गजेन्द्र शर्मा, सुरजी देवी, जय सिंह, गुरूचरन सिंह (वैध जी) के घरो की ओर मार्ग का नव निर्माण कार्य।

2 years ago

on Monday, September 18th 2023, 10:24:52 am

Technical Sanction
of ₹ 44.86 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 394/ EE Dated 18/09/2023

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Monday, February 12th 2024, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Sunday, February 25th 2024, 6:30:00 pm
0.22%
Financial Progress

1st Expenditure
of ₹ 10076 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 44.86Lacs )

a year ago

on Friday, March 1st 2024, 6:30:00 pm
0.22%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 44.86Lacs )

a year ago

on Sunday, March 3rd 2024, 6:30:00 pm
51.87%
Financial Progress

3rd Expenditure
of ₹ 2316734 (23.17 Lacs ) done.
Cummulative ₹ 23.27Lacs ( against 44.86Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
77.55%
Financial Progress

4th Expenditure
of ₹ 1152270 (11.52 Lacs ) done.
Cummulative ₹ 34.79Lacs ( against 44.86Lacs )

a year ago

on Tuesday, April 9th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, June 2nd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Wednesday, June 26th 2024, 7:09:27 am
<span class="4">Picture Id:46875</span>
PWD Uttarakahnd
Photo (ID 46875) from Site Received
Uploader : Girish Kumar, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Ch. 0.050
Remark : Work complete.

a year ago

on Sunday, July 21st 2024, 6:30:00 pm
82.44%
Financial Progress

5th Expenditure
of ₹ 219377 (2.19 Lacs ) done.
Cummulative ₹ 36.98Lacs ( against 44.86Lacs )

8 months ago

on Thursday, December 12th 2024, 6:30:00 pm
83.11%
Financial Progress

6th Expenditure
of ₹ 30000 (0.30 Lacs ) done.
Cummulative ₹ 37.28Lacs ( against 44.86Lacs )

8 months ago

on Thursday, December 19th 2024, 6:30:00 pm
83.51%
Financial Progress

7th Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 37.46Lacs ( against 44.86Lacs )

8 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
85.09%
Financial Progress

9th Expenditure
of ₹ 30680 (0.31 Lacs ) done.
Cummulative ₹ 38.17Lacs ( against 44.86Lacs )

8 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
84.41%
Financial Progress

8th Expenditure
of ₹ 40120 (0.40 Lacs ) done.
Cummulative ₹ 37.87Lacs ( against 44.86Lacs )

7 months ago

on Thursday, January 16th 2025, 6:30:00 pm
96.23%
Financial Progress

11th Expenditure
of ₹ 441072 (4.41 Lacs ) done.
Cummulative ₹ 43.17Lacs ( against 44.86Lacs )

7 months ago

on Thursday, January 16th 2025, 6:30:00 pm
86.40%
Financial Progress

10th Expenditure
of ₹ 58500 (0.58 Lacs ) done.
Cummulative ₹ 38.76Lacs ( against 44.86Lacs )

7 months ago

on Monday, January 27th 2025, 6:30:00 pm
97.32%
Financial Progress

12th Expenditure
of ₹ 48913 (0.49 Lacs ) done.
Cummulative ₹ 43.66Lacs ( against 44.86Lacs )