2 years ago

on Wednesday, October 11th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधान सभा क्षेत्र रामनगर में ग्राम पीरूमदारा के अन्तर्गत मधुवन कालोनी एवं कैलाश कुन्ज में गोलज्यू मन्दिर के समीप मार्ग का नव निर्माण कार्य।

a year ago

on Thursday, December 14th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Monday, February 12th 2024, 6:30:00 pm
47%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Friday, March 1st 2024, 6:30:00 pm
25.62%
Financial Progress

1st Expenditure
of ₹ 2309968 (23.10 Lacs ) done.
Cummulative ₹ 23.10Lacs ( against 90.15Lacs )

a year ago

on Wednesday, March 6th 2024, 6:30:00 pm
25.74%
Financial Progress

2nd Expenditure
of ₹ 10795 (0.11 Lacs ) done.
Cummulative ₹ 23.21Lacs ( against 90.15Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
28.23%
Financial Progress

3rd Expenditure
of ₹ 224200 (2.24 Lacs ) done.
Cummulative ₹ 25.45Lacs ( against 90.15Lacs )

a year ago

on Tuesday, March 26th 2024, 6:30:00 pm
65.14%
Financial Progress

4th Expenditure
of ₹ 3327133 (33.27 Lacs ) done.
Cummulative ₹ 58.72Lacs ( against 90.15Lacs )

a year ago

on Tuesday, April 9th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Wednesday, June 26th 2024, 1:41:57 am
<span class="4">Picture Id:46881</span>
PWD Uttarakahnd
Photo (ID 46881) from Site Received
Uploader : Girish Kumar, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Near Goljyu Mandir
Remark : Work comlete

9 months ago

on Sunday, July 28th 2024, 6:30:00 pm
67.01%
Financial Progress

5th Expenditure
of ₹ 169124 (1.69 Lacs ) done.
Cummulative ₹ 60.41Lacs ( against 90.15Lacs )

8 months ago

on Friday, September 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

8 months ago

on Friday, September 20th 2024, 6:30:00 pm
86.66%
Financial Progress

6th Expenditure
of ₹ 1770925 (17.71 Lacs ) done.
Cummulative ₹ 78.12Lacs ( against 90.15Lacs )

4 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
86.99%
Financial Progress

7th Expenditure
of ₹ 29618 (0.30 Lacs ) done.
Cummulative ₹ 78.42Lacs ( against 90.15Lacs )

AI layer

AI Road
AI Bridge
50 m
100 ft
Unavailable