Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधान सभा क्षेत्र रामनगर में ग्राम पीरूमदारा के अन्तर्गत मधुवन कालोनी एवं कैलाश कुन्ज में गोलज्यू मन्दिर के समीप मार्ग का नव निर्माण कार्य।
on Thursday, December 14th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Monday, February 12th 2024, 6:30:00 pm
47%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, March 1st 2024, 6:30:00 pm
25.62%
Financial Progress
1st Expenditure
of ₹ 2309968 (23.10 Lacs ) done.
Cummulative ₹ 23.10Lacs ( against 90.15Lacs )
on Wednesday, March 6th 2024, 6:30:00 pm
25.74%
Financial Progress
2nd Expenditure
of ₹ 10795 (0.11 Lacs ) done.
Cummulative ₹ 23.21Lacs ( against 90.15Lacs )
on Sunday, March 24th 2024, 6:30:00 pm
28.23%
Financial Progress
3rd Expenditure
of ₹ 224200 (2.24 Lacs ) done.
Cummulative ₹ 25.45Lacs ( against 90.15Lacs )
on Tuesday, March 26th 2024, 6:30:00 pm
65.14%
Financial Progress
4th Expenditure
of ₹ 3327133 (33.27 Lacs ) done.
Cummulative ₹ 58.72Lacs ( against 90.15Lacs )
on Tuesday, April 9th 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, June 26th 2024, 1:41:57 am
PWD UttarakahndPhoto (ID 46881) from Site Received
Uploader : Girish Kumar, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Near Goljyu Mandir
Remark : Work comlete
on Sunday, July 28th 2024, 6:30:00 pm
67.01%
Financial Progress
5th Expenditure
of ₹ 169124 (1.69 Lacs ) done.
Cummulative ₹ 60.41Lacs ( against 90.15Lacs )
on Friday, September 6th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Friday, September 20th 2024, 6:30:00 pm
86.66%
Financial Progress
6th Expenditure
of ₹ 1770925 (17.71 Lacs ) done.
Cummulative ₹ 78.12Lacs ( against 90.15Lacs )
on Tuesday, December 31st 2024, 6:30:00 pm
86.99%
Financial Progress
7th Expenditure
of ₹ 29618 (0.30 Lacs ) done.
Cummulative ₹ 78.42Lacs ( against 90.15Lacs )