10 years ago

on Thursday, July 23rd 2015, 6:30:00 pm
Work Sanctioned
रमसा के अन्तर्गत राजकीय इण्टर कालेज श्रीकोटखाल का निर्माण कार्य।

9 years ago

on Tuesday, December 6th 2016, 6:30:00 pm

Technical Sanction
of ₹ 43.37 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE letter No 1739/9C

8 years ago

on Sunday, December 31st 2017, 6:30:00 pm
8.99%
Financial Progress

1st Expenditure
of ₹ 390000 (3.90 Lacs ) done.
Cummulative ₹ 3.90Lacs ( against 43.37Lacs )

7 years ago

on Monday, April 30th 2018, 6:30:00 pm
35.93%
Financial Progress

2nd Expenditure
of ₹ 1168167 (11.68 Lacs ) done.
Cummulative ₹ 15.58Lacs ( against 43.37Lacs )

7 years ago

on Friday, November 30th 2018, 6:30:00 pm
52.79%
Financial Progress

3rd Expenditure
of ₹ 731481 (7.31 Lacs ) done.
Cummulative ₹ 22.90Lacs ( against 43.37Lacs )

6 years ago

on Sunday, June 30th 2019, 6:30:00 pm
67.88%
Financial Progress

4th Expenditure
of ₹ 654454 (6.54 Lacs ) done.
Cummulative ₹ 29.44Lacs ( against 43.37Lacs )

6 years ago

on Wednesday, July 31st 2019, 6:30:00 pm
73.42%
Financial Progress

5th Expenditure
of ₹ 240000 (2.40 Lacs ) done.
Cummulative ₹ 31.84Lacs ( against 43.37Lacs )

5 years ago

on Wednesday, September 30th 2020, 6:30:00 pm
93.86%
Financial Progress

6th Expenditure
of ₹ 886497 (8.86 Lacs ) done.
Cummulative ₹ 40.71Lacs ( against 43.37Lacs )

3 years ago

on Tuesday, December 20th 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time
Loading...

AI layer

AI Road
AI Bridge
5000 km
3000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors