Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र चैबट्टाखाल के विकासखण्ड एकेश्वर में खलेउ-पिपली-कुमराडी-सालकोट मोटर मार्ग का सुदृड़ीकरण एवं डामरीकरण का कार्य।
on Thursday, May 6th 2021, 8:02:44 am
Technical Sanction
of ₹ 62.26 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE LETTER NO. 706/TS dt 06.05.2021 of ammount 62.26 lac
on Monday, August 16th 2021, 4:06:10 am
PWD UttarakahndPhoto (ID 709) from Site Received
Uploader : Harpal Singh, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : 0.00
Remark : Proposed in NABARD27
on Wednesday, August 25th 2021, 6:30:00 pm
0.11%
Financial Progress
1st Expenditure
of ₹ 7080 (0.07 Lacs ) done.
Cummulative ₹ 0.07Lacs ( against 62.26Lacs )
on Sunday, November 14th 2021, 6:30:00 pm
0.27%
Financial Progress
2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.17Lacs ( against 62.26Lacs )
on Monday, July 11th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Monday, September 26th 2022, 6:30:00 pm
29.24%
Financial Progress
3rd Expenditure
of ₹ 1803492 (18.03 Lacs ) done.
Cummulative ₹ 18.21Lacs ( against 62.26Lacs )
on Tuesday, March 28th 2023, 6:30:00 pm
92.44%
Financial Progress
4th Expenditure
of ₹ 3935000 (39.35 Lacs ) done.
Cummulative ₹ 57.56Lacs ( against 62.26Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
92.92%
Financial Progress
5th Expenditure
of ₹ 29699 (0.30 Lacs ) done.
Cummulative ₹ 57.85Lacs ( against 62.26Lacs )
on Monday, August 26th 2024, 6:30:00 pm
93.41%
Financial Progress
6th Expenditure
of ₹ 30720 (0.31 Lacs ) done.
Cummulative ₹ 58.16Lacs ( against 62.26Lacs )
on Tuesday, March 18th 2025, 6:30:00 pm
94.68%
Financial Progress
7th Expenditure
of ₹ 78700 (0.79 Lacs ) done.
Cummulative ₹ 58.95Lacs ( against 62.26Lacs )