on Monday, June 14th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र चैबट्टाखाल के विकासखण्ड पाबौ में पाबौ-दमदेवल मोटर मार्ग के किमी 15 से 16 में सुदृढीकरण एवं डामरीकरण का कार्य।(द्वितीय चरण)
on Friday, August 13th 2021, 5:04:20 am
Technical Sanction
of ₹ 121.63 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE LETTER NO. 4237/144 याता0-12/2020 dt 13.08.2021
on Monday, November 15th 2021, 6:30:00 pm
0.16%
Financial Progress
1st Expenditure
of ₹ 18938 (0.19 Lacs ) done.
Cummulative ₹ 0.19Lacs ( against 121.63Lacs )
on Monday, November 15th 2021, 6:30:00 pm
0.24%
Financial Progress
2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.29Lacs ( against 121.63Lacs )
on Tuesday, September 27th 2022, 6:30:00 pm
28.82%
Financial Progress
3rd Expenditure
of ₹ 3476248 (34.76 Lacs ) done.
Cummulative ₹ 35.05Lacs ( against 121.63Lacs )
on Tuesday, October 11th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, March 14th 2023, 6:30:00 pm
43.44%
Financial Progress
4th Expenditure
of ₹ 1778000 (17.78 Lacs ) done.
Cummulative ₹ 52.83Lacs ( against 121.63Lacs )
on Tuesday, March 14th 2023, 6:30:00 pm
82.85%
Financial Progress
5th Expenditure
of ₹ 4793421 (47.93 Lacs ) done.
Cummulative ₹ 100.77Lacs ( against 121.63Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
86.93%
Financial Progress
6th Expenditure
of ₹ 496542 (4.97 Lacs ) done.
Cummulative ₹ 105.73Lacs ( against 121.63Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
91.57%
Financial Progress
7th Expenditure
of ₹ 564672 (5.65 Lacs ) done.
Cummulative ₹ 111.38Lacs ( against 121.63Lacs )
on Tuesday, February 25th 2025, 6:30:00 pm
93.99%
Financial Progress
8th Expenditure
of ₹ 294000 (2.94 Lacs ) done.
Cummulative ₹ 114.32Lacs ( against 121.63Lacs )