on Tuesday, November 28th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत विधानसभा क्षेत्र चैबट्टाखाल के विकासखण्ड एकेश्वर के अन्तर्गत तिलखोली मोटर मार्ग से संगलाकोटी बैण्ड से संगलाकोटी गांव तक मोटर मार्ग का नव निर्माण कार्य। द्वितीय चरण स्टेज-।
on Wednesday, May 1st 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 6th 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, July 23rd 2024, 6:30:00 pm
5.31%
Financial Progress
1st Expenditure
of ₹ 170864 (1.71 Lacs ) done.
Cummulative ₹ 1.71Lacs ( against 32.16Lacs )
on Friday, September 6th 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, March 19th 2025, 6:30:00 pm
81.00%
Financial Progress
2nd Expenditure
of ₹ 2434103 (24.34 Lacs ) done.
Cummulative ₹ 26.05Lacs ( against 32.16Lacs )