on Wednesday, September 11th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौडी गढवाल के विकासखण्ड पाबौ में रा0इ0का0 विशल्ड सेमेन सड़क तक मोटर मार्ग का डामरीकरण का कार्य।

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
8.01%
Financial Progress

1st Expenditure
of ₹ 577787 (5.78 Lacs ) done.
Cummulative ₹ 5.78Lacs ( against 72.16Lacs )

8 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
17.70%
Financial Progress

2nd Expenditure
of ₹ 699429 (6.99 Lacs ) done.
Cummulative ₹ 12.77Lacs ( against 72.16Lacs )

7 months ago

on Monday, March 17th 2025, 6:30:00 pm
17.70%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 12.77Lacs ( against 72.16Lacs )

6 months ago

on Tuesday, April 22nd 2025, 6:30:00 pm
17.70%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 12.77Lacs ( against 72.16Lacs )

5 months ago

on Monday, May 5th 2025, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 1st time

5 months ago

on Tuesday, May 6th 2025, 6:30:00 pm
26.56%
Financial Progress

5th Expenditure
of ₹ 639313 (6.39 Lacs ) done.
Cummulative ₹ 19.17Lacs ( against 72.16Lacs )

3 months ago

on Tuesday, July 1st 2025, 6:30:00 pm
40.20%
Financial Progress

6th Expenditure
of ₹ 984490 (9.84 Lacs ) done.
Cummulative ₹ 29.01Lacs ( against 72.16Lacs )

2 months ago

on Friday, August 1st 2025, 6:30:00 pm
45.25%
Financial Progress

7th Expenditure
of ₹ 364227 (3.64 Lacs ) done.
Cummulative ₹ 32.65Lacs ( against 72.16Lacs )