6 years ago

on Monday, July 8th 2019, 6:30:00 pm
Work Sanctioned
जनपद चमोली के विकासखण्ड गैरसैण में न्यायालय के स्टाफ हेतु आवासीय भवन (टाईप । एवं ।।) का निर्माण कार्य। (द्वितीय चरण)

6 years ago

on Wednesday, February 5th 2020, 6:30:00 pm

Technical Sanction
of ₹ 255.48 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 254/7(570) yata-Pauri/2020

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
9.02%
Financial Progress

1st Expenditure
of ₹ 2305627 (23.06 Lacs ) done.
Cummulative ₹ 23.06Lacs ( against 255.48Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
15.39%
Financial Progress

2nd Expenditure
of ₹ 1625335 (16.25 Lacs ) done.
Cummulative ₹ 39.31Lacs ( against 255.48Lacs )

5 years ago

on Sunday, January 31st 2021, 6:30:00 pm
20.61%
Financial Progress

3rd Expenditure
of ₹ 1335247 (13.35 Lacs ) done.
Cummulative ₹ 52.66Lacs ( against 255.48Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
26.08%
Financial Progress

4th Expenditure
of ₹ 1397786 (13.98 Lacs ) done.
Cummulative ₹ 66.64Lacs ( against 255.48Lacs )

4 years ago

on Monday, June 28th 2021, 6:30:00 pm
35.57%
Financial Progress

5th Expenditure
of ₹ 2422420 (24.22 Lacs ) done.
Cummulative ₹ 90.86Lacs ( against 255.48Lacs )

4 years ago

on Tuesday, July 6th 2021, 6:30:00 pm
44%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Thursday, July 8th 2021, 5:40:47 am
<span class="4">Picture Id:337</span>
PWD Uttarakahnd
Photo (ID 337) from Site Received
Uploader : Manoj, JE Civil (Samvida) ,PD Pauri
Landmark : 0.180 near tahsil building
Remark : Brick work progress

4 years ago

on Thursday, July 8th 2021, 5:43:48 am
<span class="4">Picture Id:618</span>
PWD Uttarakahnd
Photo (ID 618) from Site Received
Uploader : Aditya Nath Thakur, Assistant Engineer Civil ,TD Chakrata
Landmark : 0/2
Remark : Mumty slab reinforcement work is in progress .. brick work , fixing of GI tube is in progress

4 years ago

on Saturday, July 31st 2021, 6:30:00 pm
46%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Wednesday, September 1st 2021, 6:30:00 pm
48%

Physical Progress
Physical Progress Reported at 3rd time

4 years ago

on Wednesday, September 8th 2021, 6:30:00 pm
39.84%
Financial Progress

6th Expenditure
of ₹ 1091202 (10.91 Lacs ) done.
Cummulative ₹ 101.78Lacs ( against 255.48Lacs )

4 years ago

on Tuesday, September 28th 2021, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 4th time

4 years ago

on Friday, December 3rd 2021, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 5th time

4 years ago

on Thursday, December 30th 2021, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 6th time

3 years ago

on Friday, July 1st 2022, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 7th time

3 years ago

on Thursday, September 22nd 2022, 6:30:00 pm
54.04%
Financial Progress

7th Expenditure
of ₹ 3627569 (36.28 Lacs ) done.
Cummulative ₹ 138.05Lacs ( against 255.48Lacs )

3 years ago

on Monday, November 28th 2022, 6:30:00 pm
63.57%
Financial Progress

8th Expenditure
of ₹ 2435967 (24.36 Lacs ) done.
Cummulative ₹ 162.41Lacs ( against 255.48Lacs )

3 years ago

on Tuesday, January 24th 2023, 6:30:00 pm
67.70%
Financial Progress

9th Expenditure
of ₹ 1055015 (10.55 Lacs ) done.
Cummulative ₹ 172.96Lacs ( against 255.48Lacs )

3 years ago

on Wednesday, February 1st 2023, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 8th time

3 years ago

on Friday, February 24th 2023, 6:30:00 pm
79.76%
Financial Progress

10th Expenditure
of ₹ 3080472 (30.80 Lacs ) done.
Cummulative ₹ 203.77Lacs ( against 255.48Lacs )

3 years ago

on Sunday, March 19th 2023, 6:30:00 pm
83.97%
Financial Progress

11th Expenditure
of ₹ 1076933 (10.77 Lacs ) done.
Cummulative ₹ 214.54Lacs ( against 255.48Lacs )

2 years ago

on Sunday, April 2nd 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 9th time

2 years ago

on Wednesday, September 13th 2023, 6:30:00 pm
85.43%
Financial Progress

12th Expenditure
of ₹ 371137 (3.71 Lacs ) done.
Cummulative ₹ 218.25Lacs ( against 255.48Lacs )

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
86.39%
Financial Progress

14th Expenditure
of ₹ 19470 (0.19 Lacs ) done.
Cummulative ₹ 220.72Lacs ( against 255.48Lacs )

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
86.47%
Financial Progress

15th Expenditure
of ₹ 19470 (0.19 Lacs ) done.
Cummulative ₹ 220.91Lacs ( against 255.48Lacs )

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
86.54%
Financial Progress

16th Expenditure
of ₹ 19470 (0.19 Lacs ) done.
Cummulative ₹ 221.10Lacs ( against 255.48Lacs )

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
86.61%
Financial Progress

17th Expenditure
of ₹ 17522 (0.18 Lacs ) done.
Cummulative ₹ 221.28Lacs ( against 255.48Lacs )

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
95.35%
Financial Progress

18th Expenditure
of ₹ 2232080 (22.32 Lacs ) done.
Cummulative ₹ 243.60Lacs ( against 255.48Lacs )

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
86.32%
Financial Progress

13th Expenditure
of ₹ 227322 (2.27 Lacs ) done.
Cummulative ₹ 220.52Lacs ( against 255.48Lacs )

2 years ago

on Tuesday, October 24th 2023, 6:30:00 pm
95.43%
Financial Progress

19th Expenditure
of ₹ 20280 (0.20 Lacs ) done.
Cummulative ₹ 243.80Lacs ( against 255.48Lacs )

2 years ago

on Tuesday, October 24th 2023, 6:30:00 pm
95.52%
Financial Progress

20th Expenditure
of ₹ 23725 (0.24 Lacs ) done.
Cummulative ₹ 244.04Lacs ( against 255.48Lacs )

2 years ago

on Tuesday, December 12th 2023, 10:39:24 am
<span class="4">Picture Id:31946</span>
PWD Uttarakahnd
Photo (ID 31946) from Site Received
Uploader : Anirudh Rawat, Additional Assistant Engineer Civil ,PD Rudraprayag
Landmark : Near Tehsil Building
Remark : Work has been completed

2 years ago

on Wednesday, March 13th 2024, 6:30:00 pm
97.44%
Financial Progress

21st Expenditure
of ₹ 490000 (4.90 Lacs ) done.
Cummulative ₹ 248.94Lacs ( against 255.48Lacs )

2 years ago

on Thursday, March 21st 2024, 6:30:00 pm
97.80%
Financial Progress

22nd Expenditure
of ₹ 91245 (0.91 Lacs ) done.
Cummulative ₹ 249.85Lacs ( against 255.48Lacs )

2 years ago

on Thursday, March 21st 2024, 6:30:00 pm
97.94%
Financial Progress

23rd Expenditure
of ₹ 35456 (0.35 Lacs ) done.
Cummulative ₹ 250.21Lacs ( against 255.48Lacs )

a year ago

on Tuesday, May 14th 2024, 6:30:00 pm
98.54%
Financial Progress

24th Expenditure
of ₹ 154371 (1.54 Lacs ) done.
Cummulative ₹ 251.75Lacs ( against 255.48Lacs )

a year ago

on Tuesday, July 23rd 2024, 6:30:00 pm
99.43%
Financial Progress

25th Expenditure
of ₹ 226029 (2.26 Lacs ) done.
Cummulative ₹ 254.01Lacs ( against 255.48Lacs )