on Thursday, November 5th 2015, 6:30:00 pm
Work Sanctioned
जनपद चमोली के विधानसभा क्षेत्र कर्णप्रयाग के विकासखण्ड गैरसैण के अन्तर्गत दिवालीखाल-भराडीसैंण-सारकोट-सिंगग्वाड गैरसैण मोटर मार्ग का नव निर्माण।
on Monday, February 29th 2016, 6:30:00 pm
0.81%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 12.3Lacs )
on Sunday, May 31st 2020, 6:30:00 pm
5.26%
Financial Progress
2nd Expenditure
of ₹ 54750 (0.55 Lacs ) done.
Cummulative ₹ 0.65Lacs ( against 12.3Lacs )
on Tuesday, August 30th 2022, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 1st time
on Monday, September 11th 2023, 6:30:00 pm
12.39%
Financial Progress
3rd Expenditure
of ₹ 87621 (0.88 Lacs ) done.
Cummulative ₹ 1.52Lacs ( against 12.3Lacs )
on Sunday, October 20th 2024, 6:30:00 pm
12.39%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 1.52Lacs ( against 12.3Lacs )
on Wednesday, October 23rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, December 29th 2024, 6:30:00 pm
39.70%
Financial Progress
5th Expenditure
of ₹ 336000 (3.36 Lacs ) done.
Cummulative ₹ 4.88Lacs ( against 12.3Lacs )
on Sunday, January 5th 2025, 6:30:00 pm
41.77%
Financial Progress
6th Expenditure
of ₹ 25440 (0.25 Lacs ) done.
Cummulative ₹ 5.14Lacs ( against 12.3Lacs )
on Wednesday, January 15th 2025, 6:30:00 pm
51.53%
Financial Progress
7th Expenditure
of ₹ 120000 (1.20 Lacs ) done.
Cummulative ₹ 6.34Lacs ( against 12.3Lacs )
on Wednesday, January 15th 2025, 6:30:00 pm
61.29%
Financial Progress
8th Expenditure
of ₹ 120000 (1.20 Lacs ) done.
Cummulative ₹ 7.54Lacs ( against 12.3Lacs )
on Wednesday, January 15th 2025, 6:30:00 pm
74.94%
Financial Progress
9th Expenditure
of ₹ 168000 (1.68 Lacs ) done.
Cummulative ₹ 9.22Lacs ( against 12.3Lacs )