a year ago

on Tuesday, May 14th 2024, 6:30:00 pm
Work Sanctioned
श्री केदारनाथ धाम पैदल यात्रा 2024 के अंतर्गत गौरीकुंड केदारनाथ धाम पैदल मार्ग के किमी 1,5,6 व 7 में क्षतिग्रस्त स्टोन सेट सतह की मरम्मत का कार्य

5 months ago

on Friday, March 14th 2025, 6:30:00 pm
53.59%
Financial Progress

1st Expenditure
of ₹ 2110298 (21.10 Lacs ) done.
Cummulative ₹ 21.10Lacs ( against 39.38Lacs )

5 months ago

on Thursday, March 20th 2025, 6:30:00 pm
53.96%
Financial Progress

2nd Expenditure
of ₹ 14488 (0.14 Lacs ) done.
Cummulative ₹ 21.25Lacs ( against 39.38Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
54.32%
Financial Progress

3rd Expenditure
of ₹ 14273 (0.14 Lacs ) done.
Cummulative ₹ 21.39Lacs ( against 39.38Lacs )

4 months ago

on Monday, May 5th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 months ago

on Friday, May 30th 2025, 6:30:00 pm
99.15%
Financial Progress

4th Expenditure
of ₹ 1765574 (17.66 Lacs ) done.
Cummulative ₹ 39.05Lacs ( against 39.38Lacs )

a month ago

on Friday, July 18th 2025, 6:30:00 pm
99.46%
Financial Progress

5th Expenditure
of ₹ 12181 (0.12 Lacs ) done.
Cummulative ₹ 39.17Lacs ( against 39.38Lacs )

a month ago

on Friday, July 18th 2025, 6:30:00 pm
99.75%
Financial Progress

6th Expenditure
of ₹ 11254 (0.11 Lacs ) done.
Cummulative ₹ 39.28Lacs ( against 39.38Lacs )