on Wednesday, January 8th 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत विधानसभा क्षेत्र केदारनाथ में नवनिर्मित रामबाड़ा से गरूड़चट्टी तक पैदल मार्ग में स्टोन सैट एवं रेलिंग फिक्सिंग के कार्य।
on Tuesday, July 1st 2025, 6:30:00 pm
4.00%
Financial Progress
1st Expenditure
of ₹ 2287524 (22.88 Lacs ) done.
Cummulative ₹ 22.88Lacs ( against 572.04Lacs )
on Tuesday, July 1st 2025, 6:30:00 pm
10.26%
Financial Progress
2nd Expenditure
of ₹ 3581818 (35.82 Lacs ) done.
Cummulative ₹ 58.69Lacs ( against 572.04Lacs )
on Tuesday, July 1st 2025, 6:30:00 pm
15.50%
Financial Progress
3rd Expenditure
of ₹ 2999385 (29.99 Lacs ) done.
Cummulative ₹ 88.69Lacs ( against 572.04Lacs )
on Thursday, July 10th 2025, 6:30:00 pm
17.33%
Financial Progress
4th Expenditure
of ₹ 1043920 (10.44 Lacs ) done.
Cummulative ₹ 99.13Lacs ( against 572.04Lacs )
on Thursday, July 10th 2025, 6:30:00 pm
20.07%
Financial Progress
5th Expenditure
of ₹ 1565798 (15.66 Lacs ) done.
Cummulative ₹ 114.78Lacs ( against 572.04Lacs )
on Sunday, July 20th 2025, 6:30:00 pm
20.08%
Financial Progress
6th Expenditure
of ₹ 10413 (0.10 Lacs ) done.
Cummulative ₹ 114.89Lacs ( against 572.04Lacs )
on Monday, July 21st 2025, 6:30:00 pm
21.45%
Financial Progress
7th Expenditure
of ₹ 779280 (7.79 Lacs ) done.
Cummulative ₹ 122.68Lacs ( against 572.04Lacs )