6 years ago

on Monday, March 4th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना वर्ष 2018-19 के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र लक्सर के ग्राम अकौढा खुर्द में पीपलो वाले पुल से लाला घनश्याम के खेत की ओर मार्ग का निर्माण कार्य। (द्वितीय चरण)

6 years ago

on Sunday, May 12th 2019, 6:30:00 pm

Technical Sanction
of ₹ 115.54 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE SE Letter No. 861(3)/47c-c.c./19

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
36.95%
Financial Progress

1st Expenditure
of ₹ 4268891 (42.69 Lacs ) done.
Cummulative ₹ 42.69Lacs ( against 115.54Lacs )

4 years ago

on Sunday, June 6th 2021, 6:30:00 pm
49.07%
Financial Progress

2nd Expenditure
of ₹ 1400986 (14.01 Lacs ) done.
Cummulative ₹ 56.70Lacs ( against 115.54Lacs )

4 years ago

on Thursday, July 29th 2021, 6:30:00 pm
49.30%
Financial Progress

3rd Expenditure
of ₹ 26660 (0.27 Lacs ) done.
Cummulative ₹ 56.97Lacs ( against 115.54Lacs )

3 years ago

on Tuesday, March 29th 2022, 6:30:00 pm
71.31%
Financial Progress

4th Expenditure
of ₹ 2542792 (25.43 Lacs ) done.
Cummulative ₹ 82.39Lacs ( against 115.54Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
71.88%
Financial Progress

5th Expenditure
of ₹ 65613 (0.66 Lacs ) done.
Cummulative ₹ 83.05Lacs ( against 115.54Lacs )

3 years ago

on Saturday, October 29th 2022, 6:30:00 pm
92.93%
Financial Progress

6th Expenditure
of ₹ 2432548 (24.33 Lacs ) done.
Cummulative ₹ 107.37Lacs ( against 115.54Lacs )

2 years ago

on Monday, April 24th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 months ago

on Sunday, May 25th 2025, 6:30:00 pm
93.88%
Financial Progress

7th Expenditure
of ₹ 109502 (1.10 Lacs ) done.
Cummulative ₹ 108.47Lacs ( against 115.54Lacs )